In the Matter of

)

)

Alan Field

)

File No.: EB-FIELDWR-14-00015831

Antenna Structure Owner

)

)

Citation No.: C201432900005

Los Angeles, California

)

CITATION AND ORDER

Failure to Obtain Antenna Structure Registration

Adopted: July 23, 2014

Released: July 24, 2014

By the District Director, Los Angeles Office, Western Region, Enforcement Bureau:

I.

INTRODUCTION

1.

This is an official CITATION AND ORDER (Citation) issued pursuant to Section

503(b)(5) of the Communications Act of 1934, as amended (Communications Act or Act),1 to Alan Field,

owner of the antenna structure (Antenna Structure) located at 11231 S. La Cienega Blvd., Los Angeles,

California. Specifically, Mr. Field is being cited for failing to register with the Federal Communications

Commission (Commission) an Antenna Structure that requires notice to the Federal Aviation

Administration (FAA) in violation of Section 17.4(a) of the Commission’s rules (Rules).2

2.

Notice of Duty to Comply With Laws: Mr. Field should take immediate steps to come

into compliance with the Rules, and to avoid any recurrence of the misconduct, specifically, failing to

register the Antenna Structure with the Commission. Mr. Field is hereby on notice that if he

subsequently engages in any conduct of the type described in this Citation, including any violation of

Section 17.4(a) of the Rules, he may be subject to civil and criminal penalties, including but not limited to

substantial monetary fines (forfeitures). Such forfeitures may be based on both the conduct that led to this

Citation and the conduct following it.3

3.

Your Response Required: Pursuant to Sections 4(i), 4(j), and 403 of the Communications

Act,4 we also direct Mr. Field to respond in writing, within thirty (30) calendar days after the release date

1 47 U.S.C. § 503(b)(5). Section 503(b)(5) of the Act provides that a Citation is not required in the case of

violations of Section 303(q) of the Act, 47 U.S.C. § 303(q), if the person/entity involved is a nonlicensee tower

owner who has previously received notice of the obligations imposed by Section 303(q) from the Commission or the

permittee or licensee who uses that tower. In this case, however, we are providing a Citation to Mr. Field because

such notice may not have been previously provided. See North Chapel Investments, Citation and Order, 27 FCC

Rcd 4813 (Enf. Bur. 2012) (citation issued to nonlicensee antenna structure owner which may not have had notice of

its obligations concerning its antenna structures).

2 47 C.F.R. §§ 17.4(a).

3 See 47 U.S.C § 503(b)(5). See also S. Rep. No. 95-580, 95th Cong., 1st Sess. at 9 (1977) (If a person or entity that

has been issued a citation by the Commission thereafter engages in the conduct for which the citation of violation

was sent, the subsequent notice of apparent liability “would attach not only for the conduct occurring subsequently

but also for the conduct for which the citation was originally sent.”) (emphasis added).

4 47 U.S.C. §§ 154(i), 154(j), 403.

image02-00.jpg612x792

Federal Communications Commission

DA 14-1038

of this Citation, and signed under penalty of perjury, with descriptions of the specific action(s) taken to

preclude recurrence of the violations, and also a timeline for completion of any correction action(s).

II.

BACKGROUND

4.

On December 4, 2013, in response to a complaint, an agent of the Enforcement Bureau’s

Los Angeles Office (Los Angeles Office) observed an antenna structure with an overall height of

approximately 100 feet (30 meters) located at 11231 S. La Cienega Blvd., Los Angeles, California and

near the Los Angeles International Airport (approximate geographic coordinates of 33° 55’ 58” north

latitude, 118° 22’ 15” west longitude). The agent observed that there was no Antenna Structure

Registration number posted at or near the structure. The agent also observed that the structure did not

have painting or obstruction lighting.

5.

Based upon the Antenna Structure’s location and height, particularly given its proximity

to both Los Angeles International Airport and Jack Northrop Field/Hawthorne Municipal Airport, the Los

Angeles Office determined that the Antenna Structure required FAA notification and FCC registration.

Finding that the Antenna Structure was not registered with the Commission and that no notice to airmen

(NOTAM) had been issued for the Antenna Structure, the Los Angeles Office asked the FAA to issue a

NOTAM for the structure, and has continued to renew the NOTAM.5 Although the Antenna Structure is

apparently not being presently used for radio transmissions, the Antenna Structure still supports two

microwave transmission antennas.6 A Letter of Inquiry concerning the lack of the antenna structure

registration was sent from the Los Angeles Office to Mr. Field, but no response was received. 7

III.

APPLICABLE LAW AND VIOLATIONS

6.

Section 17.4(a) of the Rules mandates that an antenna structure that requires notice to the

FAA must be registered with the Commission.8 Section 17.7 of the Rules specifies that “[a] notification

to the FAA is required, except as set forth in 17.14, for any of the following construction or altercation:

(a) Any construction or alteration of more than 60.96 meters (200 feet) in height above ground level at its

site. (b) Any construction or alteration of greater height than an imaginary surface extending outward and

upward at one of the following slopes: (1) 100 to 1 for horizontal distance of 6.10 kilometers (20,000

feet) from the nearest point of the nearest runway of each airport specified in paragraph (d) of this section

with at least one runway more than 0.98 kilometers (3,200 feet) in actual length, excluding heliports. (2)

50 to 1 for a horizontal distance of 3.05 kilometers (10,000 feet) from the nearest point of the nearest

runway of each airport specified in paragraph (d) of this section with its longest runway no more than

0.98 kilometers (3,200 feet) in actual length, excluding heliports. (3) 25 to 1 for a horizontal distance of

5 NOTAMs alert aircraft pilots of potential hazards, including antenna structure light outages, which could affect

flight safety. See Section 17.48 of the Rules, 47 C.F.R. § 17.48. We caution Mr. Field that, as the antenna structure

owner, he must report immediately by telephone or telegraph to the nearest Flight Service Station or office of the

FAA any observed or otherwise known extinguishment or improper functioning of any required top steady burning

light or any required flashing obstruction light, regardless of its position on the antenna structure, not corrected

within 30 minutes.

6 If the Antenna Structure is no longer being used for the transmission of radio energy, Mr. Field is required to

maintain any required painting and lighting requirements assigned to the structure until the structure is dismantled.

See 47 U.S.C. § 303(q).

7 See Alan Field, Letter of Inquiry (Dec. 19, 2013) (on file in EB-FIELDWR-14-00015831).

8 47 C.F.R. § 17.4(a).

2

image03-00.jpg612x792

Federal Communications Commission

DA 14-1038

1.52 kilometers (5,000 feet) from the nearest point of the nearest landing and takeoff area of each heliport

specified in paragraph (d) of this section.” 9

7.

The record in this case shows that, on December 4, 2013, a Los Angeles agent observed

the Antenna Structure and determined that, given the Antenna Structure’s height and proximity to two

airports, it required notice to the FAA. Subsequent investigation revealed that no notification to the FAA

had apparently occurred and consequently no air safety study had been conducted or issued for the

Antenna Structure, nor had the structure been registered with the Commission. Based on the foregoing

evidence, we find that Mr. Field violated Section 17.4(a) of the Rules.10

IV.

REQUEST FOR INFORMATION

8.

Pursuant to Sections 4(i), 4(j), and 403 of the Act,11 Mr. Field is directed to confirm in

writing that he has taken the necessary measures and made the corrections to ensure that he does not

continue to violate the rules discussed above, and provide the information requested below within thirty

(30) calendar days after the release date of this Citation. A failure to respond in writing, or the provision

of an inadequate, incomplete, or misleading response, may subject Mr. Field to additional sanctions.

i.

Provide the record of FAA notification and FCC antenna structure registration.

ii.

Provide the plan for installing a lighting system for the Antenna Structure and for

painting the Antenna Structure if required to do so by FAA Aeronautical

Determination. Include a time-frame for such installation and painting.

iii.

Provide the plan for requesting an FAA NOTAM on a timely basis (to ensure air

navigation safety) until the tower is lit and painted. Include a time-frame for

such requests.

iv.

If it is believed that painting and lighting of the Antenna Structure is not

required, provide a copy of the FAA Determination of No Aeronautical Hazard

with those specifications.

V.

RESPONDING TO THIS CITATION

9.

In addition to the required written information described in paragraphs 3 and 8, above,

Mr. Field may, if he so chooses, respond to this Citation—challenging the factual and legal findings

herein—within thirty (30) calendar days from the release date of this Citation either through (1) a written

statement, (2) a teleconference interview, or (3) a personal interview at the Commission Field Office

nearest to your place of business.

10.

If you would like to arrange a teleconference or personal interview, please contact

Charles A. Cooper at (562) 860-7474. The nearest Commission Field Office is located in Cerritos,

California. Such teleconference or interview must take place within thirty (30) calendar days of the date

of this Citation. If you would like to submit a written response, including any supporting documentation,

9 47 C.F.R. § 17.7.

10 47 C.F.R. §§ 17.4(a).

11 47 U.S.C. §§ 154(i), 154(j), 403.

3

image04-00.jpg612x792

Federal Communications Commission

DA 14-1038

you must send the response within thirty (30) calendar days of the date of this Citation to the contact and

address provided in paragraph 11, below.

11.

All written communications, including the information requested in paragraphs 3 and 8,

above, should be provided to the address below.

Federal Communications Commission

Los Angeles District Office

18000 Studebaker Road, Suite 660

Cerritos, California 90703

Re: EB-FIELDWR-14-00015831

12.

Reasonable accommodations for people with disabilities are available upon request.

Include a description of the accommodation you will need, and include as much detail as you can. Also

include a way we can contact you if we need more information. Please allow at least five (5) business

days advance notice; last minute requests will be accepted, but may be impossible to fill. Send an e-mail

to fcc504@fcc.gov or call the FCC’s Consumer & Governmental Affairs Bureau:

For sign language interpreters, CART, and other reasonable accommodations:

202-418-0530 (voice), 202-418-0432 (tty);

For accessible format materials (braille, large print, electronic files, and audio format):

202-418-0531 (voice), 202-418-7365 (tty).

13.

Please be advised that it is a violation of Section 1.17 of the Rules (47 C.F.R. § 1.17) for

any person or a staff member of that person to make any false or misleading written or oral statement of

fact. Specifically, no person shall:

(1) In any written or oral statement of fact, intentionally provide material factual

information that is incorrect or intentionally omit material information that is

necessary to prevent any material factual statement that is made from being

incorrect or misleading; and

(2) In any written statement of fact, provide material factual information that is

incorrect or omit material information that is necessary to prevent any material

factual statement that is made from being incorrect or misleading without a

reasonable basis for believing that any such material factual statement is correct

and not misleading.12

14.

Further, the knowing and willful making of any false statement, or the concealment of

any material fact, in reply to this Citation is punishable by fine or imprisonment under 18 U.S.C. § 1001.

15.

If you violate Section 1.17 of the Rules or the criminal statute referenced above, you may

be subject to further legal action, including monetary fines pursuant to Section 503 of the Act.13

16.

Under the Privacy Act of 1974, 5 U.S.C. § 552a(e)(3), we are informing you that the

Commission’s staff will use all relevant material information before it, including information that you

12 47 C.F.R. § 1.17.

13 47 U.S.C. § 503.

4

image05-00.jpg612x792

Federal Communications Commission

DA 14-1038

disclose in your interview or written statement, to determine what, if any, enforcement action is required

to ensure your compliance with the Act and the Rules.

VI.

FUTURE VIOLATIONS

17.

If, after receipt of this Citation, Mr. Field again violates Section 17.4(a) of the Rules by

engaging in conduct of the type described herein, the Commission may impose monetary forfeitures not

to exceed $16,000 for each such violation or each day of a continuing violation, and up to $122,500 for

any single act or failure to act.14

Further, as discussed above, such forfeitures may be based on both the

conduct that led to the Citation and the conduct following it.15 In addition, violations of the Act or the

Rules also can result in seizure of equipment through in rem forfeiture actions,16 as well as criminal

sanctions, including imprisonment.17

VII.

ORDERING CLAUSES

18.

IT IS ORDERED that, pursuant to Sections 4(i), 4(j), and 403 of the Communications

Act, Mr. Field must provide the written information requested in paragraphs 3 and 8, above. The

response to the request for information must be provided in writing, signed under penalty of perjury by

Mr. Field, certifying personal knowledge of the information and representations provided in the written

response, and must be received by the FCC within thirty (30) calendar days after the release date of this

Citation and Order.

19.

IT IS FURTHER ORDERED that a copy of this Citation and Order shall be sent both

by First Class U.S. Mail and Certified Mail, Return Receipt Requested, to Alan Field, at his address of

record.

FEDERAL COMMUNICATIONS COMMISSION

Charles A. Cooper

District Director

Los Angeles Office

Western Region

Enforcement Bureau

14 See 47 U.S.C. §§ 401, 501, 503; 47 C.F.R. § 1.80(b)(7). This amount is subject to further adjustment for inflation

(see 47 C.F.R. § 1.80(b)(9)), and the forfeiture amount applicable to any violation will be determined based on the

statutory amount designated at the time of the violation.

15 See supra para. 2.

16 See 47 U.S.C. § 510.

17 See 47 U.S.C. §§ 401, 501.

5

Note: We are currently transitioning our documents into web compatible formats for easier reading. We have done our best to supply this content to you in a presentable form, but there may be some formatting issues while we improve the technology. The original version of the document is available as a PDF, Word Document, or as plain text.

close
FCC

You are leaving the FCC website

You are about to leave the FCC website and visit a third-party, non-governmental website that the FCC does not maintain or control. The FCC does not endorse any product or service, and is not responsible for, nor can it guarantee the validity or timeliness of the content on the page you are about to visit. Additionally, the privacy policies of this third-party page may differ from those of the FCC.