Released: August 20, 2014
image01-00.jpg612x792

Federal Communications Commission

Washington, D.C. 20554

August 20, 2014

DA 14-1196

ET Docket No. 13-49

Ms. Jenny Prime

Director, Regulatory Affairs

Public Policy Office

Cox Communications, Inc.

975 F Street NW, Suite 300

Washington, D.C. 20004

Dear Ms. Prime:

The Office of Engineering and Technology (OET) is granting the request of Cox

Communications, Inc.(Cox) for a waiver of Section 15.407(a)(1)(i)1 of the Commission’s

rules to allow its existing systems that were previously certified for operation in the 5725-

5850 MHz (U-NII-3) band to obtain FCC certification for operation in the 5150-5250 MHz

(U-NII-1) band.

In your letter filed July 2, 2014, you state that granting this waiver request will allow Cox to

operate its existing U-NII-3 band Wi-Fi systems in the U-NII-1 band.2

You submit this

waiver to allow Cox to operate its U-NII-3 band Wi-Fi systems in the U-NII-1 band with up

to 250 mW of conducted power and a PSD of 11 dBm/MHz with a 6 dBi gain antenna. In

addition, your request this waiver for 2,346 devices, deployed prior to June 2, 2014, that are

not covered by a permissive change. In addition, you provide the general location of Cox's

devices by state, as well as the total number of devices per state and request confidential

treatment for this information under separate cover.3

You also confirm that all of the devices

identified in this request can be reprogrammed to operate in the U-NII-1 band at the 250 mW

operational parameters and that the operating power of each of these devices can be adjusted

from a central network management system. 4

In the First Report and Order (First R&O) in U-NII 5 GHz proceeding, the Commission

adopted rule Section 15.407(a)(1)(a) which allows fixed outdoor access points in the U-NII-1

band at a maximum conducted output power level not to exceed 1 W and a PSD not to

exceed 17 dBm/MHz with an allowance for a 6 dBi antenna gain; the rule limits the

1 See 47 C.F.R § 15.407 (a)(1)(i).

2 See Cox Communications, Inc. Request for Waiver of Certain Technical Requirements in UNII-1 Band

(Request) dated July 2, 2014, from Jenny Prime, Cox Communications, Inc.

3 See Cox Communications, Inc. Request for Waiver of Certain Technical Requirements in UNII-1 Band –

Request for Confidential Treatment, dated July 2, 2014, from Jenny Prime, Cox Communications, Inc.

4 See Request at 2.

image02-00.jpg612x792

Jenny Prime

August 20, 2014

Page 2 of 3

maximum EIRP to 125 mW (21 dBm) at any elevation angle above 30 degrees measured

from the horizon.5

In other words, each outdoor access point must limit the energy directed

upward so that, in the aggregate, they would avoid causing interference to satellites operating

in the U-NII-1 band.6

The Commission recognized that some U-NII-3 fixed access points

already deployed could potentially be reprogrammed to meet the new U-NII-1 power limits

and thus quickly begin more flexible operation in the U-NII-1 band using this exiting

equipment.7

The Commission stated that, if outdoor U-NII-3 band systems installed prior to

the effective date of the new rules were not able to comply with the 125 mW EIRP

requirements of Section 15.407(a)(1)(i) to limit energy directed upward, manufacturers or

equipment operators could file for a waiver of this provision for operation in the U-NII-1

band,8 no later than 30 days after of the effective date of the new rules. The Commission

stated that if the waiver is designed to enable existing deployments to operate with up to 250

mW of conducted power and a PSD of 11 dBm/MHz with a 6 dBi gain antenna, the

Commission could make a quick and likely favorable good cause determination sufficient to

grant the waiver request.

The Commission asked for the following information about the petitioner’s existing

deployments to assess the waiver requests: the number of devices installed, general location

of each deployment, ability to reprogram the devices, and ability to adjust operating power

from a central network management system. The Commission concluded that waiver

requests meeting these parameters and made within a short period of time are likely to serve

the public interest because granting them is highly unlikely to create any risk of harmful

interference, given the small numbers involved and the limited departure from the new

technical requirements for the U-NII-1 band.9

In addition, the comparatively small number

of installed devices strongly suggests a negligible risk of harmful interference from allowing

this exception and the expedient approval of such waivers would benefit the public by

promptly and efficiently expanding broadband use in this band.10

The Commission delegated

authority to the Office of Engineering and Technology to consider and act on all such waiver

petitions received within 30 days of the effective date of the new rules, i.e., June 2, 2014.11

We find that the information you provide regarding the existing deployed systems satisfies

the requirements the Commission outlined in the First R&O for OET to act on your waiver

5 See, Revision of Part 15 of the Commission’s Rules to Permit Unlicensed National Information

Infrastructure (U-NII) Devices in the 5 GHz Band, First Report and Order, ET Docket No. 13-49 , 29 FCC

Rcd. 4127 (2014) (First R&O) at 4138.

6 Id. at 4138.

7 Id. at 4139.

8 Id. at 4139 – 4140. See also 47 C.F.R. § 1.3. See also WAIT Radio v. FCC, 418 F.2d 1153 (1969).

9 See First Report and Order at 4139.

10 Id. at 4140.

11 Id.

image03-00.jpg612x792

Jenny Prime

August 20, 2014

Page 3 of 3

request, and we conclude that a waiver of Section 15.407 (a)(1)(i) is in the public interest.

That is, these currently deployed systems should not pose a threat of harmful interference to

the incumbent services in the U-NII-1 band because, as you represent, these systems can be

reprogrammed for operation in the U-NII-1 band at the 250 mW operational parameters and

the operating power can be adjusted from a central network management system. This

waiver applies only to the 2,346 outdoor access points systems at the locations that you

identify as being installed in the field as of June 2, 2014, and does not apply to any future

deployments. If you have the need to change the location, but not the total number, of your

deployments, please provide OET with the modified deployment information. You must

demonstrate compliance with the technical requirements through the equipment certification

process by filing a permissive change request along with a copy of the approved waiver.

Accordingly, pursuant to the delegated authority in Sections 0.31 and 0.241 of the

Commission’s rules and Section 1.3 of the Commission’s rules, 47 C.F.R. §§ 0.31, 0.241,

1.3, we waive the requirements of Section 15.407(a)(1)(i) of our rules to allow Cox

Communications, Inc. to obtain FCC certification, consistent with the terms of this waiver,

for the U-NII-3 band outdoor access points you have identified to operate in the U-NII-1

band with up to 250 mW of conducted power and a PSD of 11 dBm/MHz with a 6 dBi

antenna gain.

Sincerely,

Julius P. Knapp

Chief

Office of Engineering and Technology

Note: We are currently transitioning our documents into web compatible formats for easier reading. We have done our best to supply this content to you in a presentable form, but there may be some formatting issues while we improve the technology. The original version of the document is available as a PDF, Word Document, or as plain text.

close
FCC

You are leaving the FCC website

You are about to leave the FCC website and visit a third-party, non-governmental website that the FCC does not maintain or control. The FCC does not endorse any product or service, and is not responsible for, nor can it guarantee the validity or timeliness of the content on the page you are about to visit. Additionally, the privacy policies of this third-party page may differ from those of the FCC.