Maricopa County, Arizona

Download Options

Released: April 10, 2014

Federal Communications Commission

DA 14-482

Before the

Federal Communications Commission

Washington, D.C. 20554

In the Matter of
)
)

MARICOPA COUNTY, ARIZONA
)
)

WT Docket No. 02-55
Request for Extension of Time
)

ORDER

Adopted: April 10, 2014

Released: April 10, 2014

By the Deputy Chief, Policy and Licensing Division Public Safety and Homeland Security Bureau:

I.

INTRODUCTION

1.
Under consideration is the Further Request for Extension of Time (Request) filed March
10, 2014 by Maricopa County, Arizona (Maricopa). For the reasons set out below, the Request is denied
and Maricopa is directed to file a cost estimate for reconfiguration of its 800 MHz communications
system on or before July 14, 2014.

II.

BACKGROUND

2.
This is the second request for extension of time Maricopa has filed. Previously,
Maricopa requested an extension until June 1, 2014. The Public Safety and Homeland Security Bureau
denied that extension request and directed Maricopa to file a cost estimate by March 10, 2014 or request a
further extension. March 10, 2014 passed without Maricopa filing a cost estimate. On that date,
Maricopa filed the instant request, seeking an extension until October 30, 2014, five months longer than
the June 1, 2014 filing date it initially requested. Maricopa attributes its failure to file a timely cost
estimate to unspecified “unexpected delays [that] have resulted in the inability to execute the contract
between Motorola and Maricopa.”1

III.

DISCUSSION

3.
As of the date the Commission set for submission of a cost estimate, Maricopa had yet to
sign a contract with its vendor to perform the work necessary to develop that estimate. Its request for a
further extension rests on the bare claim of “unexpected delays” in executing the contract. Maricopa –
which previously represented to the Commission that it would have a cost estimate by May 1, 2014 – now
claims that the “current workload” of its vendor precludes receipt of a cost estimate before the “end of
September, 2014.”
4.
Maricopa’s filing contains no explanation of the reasons for the delay in concluding a
contract with its vendor, much less any evidence that Maricopa has attempted to accelerate the process.
The filing is absent any statement from its vendor that its “current workload” precludes producing a
timely cost estimate, much less a description of that workload. We note, however, that on June 5, 2013,

1 Request at 2.
1

Federal Communications Commission

DA 14-482

the Maricopa Board of Supervisors signed a contract with the same vendor for an upgrade to Maricopa’s
800 MHz public safety radio system.
5.
To the extent that Maricopa’s vendor’s precluding “workload” is associated with
upgrading Maricopa’s existing system, we are not persuaded that an extension of time to complete a cost
estimate is warranted. The upgrade and the provision of a cost estimate may and should proceed in
parallel. Indeed, much of the information required for the cost estimate – an assessment of the cost of
rebanding Maricopa’s pre-upgrade system – can be gathered concurrently with the upgrade process.

IV.

DECISION

6.
Maricopa falls far short of demonstrating good cause why the Commission should grant
it an extension of time to furnish a cost estimate. By submitting successive extension requests grounded
on such insubstantial excuses as “unexpected delays,” Maricopa apparently believes it is entitled to
extensions as a matter of routine. It is, however, “the policy of the Commission that extensions of time
will not routinely be granted.”2
7.
To ensure that Maricopa and its vendor devote their time and resources to producing a
cost estimate within a reasonable time, we impose the following conditions:
 Until Maricopa executes a contract with its vendor for the provision of a cost estimate, it
shall report each business day to the 800 MHz Transition Administrator on the status of
contract negotiations, including, without limitation, any issues remaining in controversy
and the positions of the parties on said issues.
 Until Maricopa’s vendor provides Maricopa with a Statement of Work, Maricopa shall
report each week to the 800 MHz Transition Administrator on the status of the work in
progress, including, without limitation, the estimated time remaining until a Statement of
Work can be provided.
 Upon receipt of a Statement of Work from its vendor, Maricopa shall incorporate its
internal costs and submit a cost estimate to Sprint and the 800 MHz Transition
Administrator within 15 working days.
 In the event that a cost estimate is not filed by July 14, 2014 Maricopa shall file a
competent request for extension of time within which to file a cost estimate. Such a
request shall be supported, at a minimum, by declarations under penalty of perjury as to
all facts alleged in the request, shall contain a detailed description of why the cost
estimate was not filed by July 14, 2014, shall be signed by a licensee principal and shall
provide a day-by-day timetable for completion of the cost estimate.

2 47 C.F.R. § 1.46.
2

Federal Communications Commission

DA 14-482

V.

ORDERING CLAUSES

8.
Accordingly, IT IS ORDERED, that the Further Request for Extension of Time, filed
March 10, 2104 by Maricopa County, Arizona, IS DENIED.
9.
IT IS FURTHER ORDERED that Maricopa County, Arizona, SHALL COMPLY with
the reporting requirements herein.
10.
This action is taken under delegated authority pursuant to Sections 0.191 and 0.392 of the
Commission’s rules, 47 C.F.R. §§ 0.191, 0.392.
FEDERAL COMMUNICATIONS COMMISSION
Michael J. Wilhelm
Deputy Chief
Policy and Licensing Division
Public Safety and Homeland Security Bureau
3

Note: We are currently transitioning our documents into web compatible formats for easier reading. We have done our best to supply this content to you in a presentable form, but there may be some formatting issues while we improve the technology. The original version of the document is available as a PDF, Word Document, or as plain text.

close
FCC

You are leaving the FCC website

You are about to leave the FCC website and visit a third-party, non-governmental website that the FCC does not maintain or control. The FCC does not endorse any product or service, and is not responsible for, nor can it guarantee the validity or timeliness of the content on the page you are about to visit. Additionally, the privacy policies of this third-party page may differ from those of the FCC.