Released: April 4, 2014
Federal Communications Commission
DA 14-461

Before the

Federal Communications Commission

Washington, D.C. 20554

In the Matter of
)
)

Implementation of Section 304 of the
)
CS Docket No. 97-80
Telecommunications Act of 1996
)
)

Tivo’s Request for Clarification or
)
Waiver of the Audiovisual Output Requirement of )
Section 76.640(b)(4)(iii)
)
)
)
)
)
)

MEMORANDUM OPINION AND ORDER

Adopted: April 3, 2014

Released: April 4, 2014

By the Chief, Media Bureau:

I.

INTRODUCTION

1.
In this Order, we grant, in part, an unopposed request from TiVo Inc. seeking waiver of
the compliance date of Section 76.640(b)(4)(iii) of the Commission’s rules, which requires cable set-top
boxes to include a recordable, Internet Protocol (“IP”)-based output.1 This waiver is pursuant to Section
629(c) of the Communications Act2 and Sections 1.3 and 76.7 of the Commission’s rules,3 and will permit
TiVo and cable operators until June 1, 2015 to comply. We also grant small cable operators until
September 1, 2015 to comply because of the difficulty they may have obtaining compliant equipment to
meet the June 1, 2015 deadline.

II.

BACKGROUND

2.
In 2003, the Commission adopted Section 76.640 of its rules. Section 76.640 has two
purposes: (1) to “facilitate[e] the direct connection of unidirectional digital cable televisions and products
to cable systems nationwide,”4 and (2) to “set a baseline of connectivity ensuring that cable subscribers
are able to fully enjoy the range of services offered by their cable provider in a secure, digital format.”5
The issue raised in TiVo’s petition is related to the second purpose; the regulation adopted in 2003


1 47 C.F.R. § 76.640(b)(4)(iii). Implementation of Section 304 of the Telecommunications Act of 1996; Commercial
Availability of Navigation Devices
, Third Report and Order and Order on Reconsideration, 25 FCC Rcd 14657,
14677-9, ¶¶ 39-44 (2010) (“2010 CableCARD Order”).
2 47 U.S.C. § 549(c).
3 47 C.F.R. §§ 1.3, 76.7.
4 Implementation of Section 304 of the Telecommunications Act of 1996; Commercial Availability of Navigation
Devices
, Second Report and Order and Second Further Notice of Proposed Rulemaking, 18 FCC Rcd 20885, 20894,
¶ 17 (2003) (“2003 CableCARD Order”).
5 2003 CableCARD Order, 18 FCC Rcd at 20897, ¶ 24.

Federal Communications Commission
DA 14-461
required cable operators to include an IEEE-1394 interface and to comply with standards that would
allow subscribers to control their set-top boxes through their television set remotes via that interface.6
3.
In 2010, the Commission realized that consumer interest in the IEEE-1394 interface had
waned, and that consumers were using interfaces other than IEEE-1394 to network their consumer
electronics devices. Therefore, the Commission modified Section 76.640(b)(4)(iii) of its rules to replace
the IEEE-1394 requirement with one that requires cable operators to “ensure that the cable-operator-
provided high definition set-top boxes, except unidirectional set-top boxes without recording
functionality, shall comply with an open industry standard that provides for audiovisual communications
including service discovery,7 video transport,8 and remote control command pass-through9 standards for
home networking.”10 This rule was intended to ensure that cable subscribers could attach devices that
they own to their cable boxes and control the boxes via the remotes of their owned devices.11 Although
the rule was originally set to go into effect on December 1, 2012, the Media Bureau granted an extension
to TiVo and cable operators that lease set-top boxes to subscribers until June 2, 2014 to allow for further
development of an open industry standard that complies with the rule.12 TiVo now seeks an extension of
this waiver until “compliance is achievable on an industry-wide basis that includes TiVo,”13 or, in the
alternative, that we clarify that the rule is not in effect in the wake of the D.C. Circuit’s decision in
Echostar Satellite, LLC v. FCC.14


6 2003 CableCARD Order, 18 FCC Rcd at 20934 (adopting new rule 47 C.F.R. § 76.640(b)(4)).
7 Service discovery refers to the protocols that a retail device would use to seamlessly recognize a leased set-top box
and the services (e.g., video programming) available on a home network. See Video Device Competition;
Implementation of Section 304 of the Telecommunications Act of 1996: Commercial Availability of Navigation
Devices; Compatibility Between Cable Systems and Consumer Electronics Equipment
, 25 FCC Rcd 4275, 4285-6, ¶
30, n.53 (2010).
8 Video transport refers to the protocols that a leased set-top box and a retail device would use to transfer digitally
encoded video from the leased set-top box to the retail device. See Internet Engineering Task Force, Audio/Video
Transport, http://datatracker.ietf.org/wg/avt/charter/ (last visited March 4, 2014).
9 Remote control command pass-through refers to the ability of a television to pass remote control commands
entered with the television remote control through to the set-top box (rather than having to use the set-top box
remote control). 2010 CableCARD Order, 25 FCC Rcd at 14677-9, ¶¶ 40, 44.
10 TiVo Inc.'s Request for Clarification and Waiver of the Audiovisual Output Requirement of Section
76.640(b)(4)(iii)
, 27 FCC Rcd 14875, 14875-6, ¶ 2 (MB 2012) (footnotes in original) (“IP-Output Waiver Order”);
47 C.F.R. § 76.640(b)(4)(iii); 2010 CableCARD Order, 25 FCC Rcd at 14677-9, ¶¶ 39-44. Pursuant to section
76.640(b)(4)(ii), this output must also be “capable of delivering recordable high definition video and closed
captioning data in an industry standard format.” 47 C.F.R. § 76.640(b)(4)(ii).
11 2010 CableCARD Order, 25 FCC Rcd at 14677-9, ¶¶ 39-44.
12 IP-Output Waiver Order, 27 FCC Rcd at 14882-5, ¶¶ 14-18. The Bureau granted operators that serve 400,000 or
fewer subscribers until September 2, 2014 to comply with the rule. Id. at 14884, ¶ 17.
13 TiVo Petition at 3-4 (filed January 3, 2014).
14 TiVo argues that the rule remains in effect after the Echostar decision and states that its request for waiver is
“premised on the assumption that Section 76.640(b)(4)(iii) remains an active regulation.” Id. at 4; TiVo Reply at 2-
3. NCTA, on the other hand, argues in its comments that Section 76.640(b)(4)(iii) is no longer effective after the
Echostar decision but that nonetheless the cable industry is implementing the rule through continued DLNA device
development. NCTA Comments at 2-4. As TiVo notes, the Commission has not yet opined on whether the rule is
effective after the D.C. Circuit’s decision in Echostar Satellite, LLC v. FCC, 704 F.3d 992 (D.C. Cir. 2013). TiVo
Petition at 2. In light of the approaching regulatory deadline, and to provide the Commission time to resolve the
issue concerning the continued effectiveness of the rule, we have decided, for the reasons stated above, to grant a
further extension of the deadline of Section 76.640(b)(4)(iii), without determining whether the rule remains in effect
after Echostar.
2

Federal Communications Commission
DA 14-461

III.

DISCUSSION

4.
We grant, in part, TiVo’s petition. Specifically, rather than grant the open-ended
extension that TiVo requests, we find that a further waiver of the IP-based output rule until June 1, 2015
is appropriate under the waiver standard set forth in Section 629(c) of the Communications Act and
Sections 1.3 and 76.7 of the Commission’s rules. We reach this conclusion for the same reasons relied
upon in the IP-Output Waiver Order.15 In that order, we found that the prediction about finalized
standards had not materialized, that DLNA had not finalized a specification that would provide all of the
required features, and that participants expected that work to be settled in early2013.16 Therefore, we
extended the compliance deadline to June 2, 2014. The record in response to TiVo’s current petition
reflects that our prediction that the standard would be settled in early 2013 was incorrect.17 We now
conclude, as we did in the IP-Output Waiver Order, that waiving the IP-based output rule to allow
development of the new DLNA standard is in the public interest because it will assist the introduction of a
new home networking technology.18 This conclusion has unanimous support in the record in response to
TiVo’s current petition.19 Based on the current record, we believe that an extension until June 1, 2015
should allow sufficient time for the standard to be finalized and for TiVo and cable operators to
implement it because the standards development process is approximately one year behind the schedule
we predicted in the IP-Output Waiver Order.20
5.
We also conclude that “an additional brief extension of the compliance period for small
cable operators is appropriate.”21 As we explained in the IP-Output Waiver Order, small cable operators
typically have difficulty obtaining compliant devices in the same timeframe as large operators.22 In its
reply comments, ACA indicates that this is still the case.23 Therefore, we grant small cable companies—
as defined in our rules as those that serve 400,000 or fewer subscribers over one or more cable
systems24—until September 1, 2015 to comply with our rule.


15 IP-Output Waiver Order, 27 FCC Rcd at 14882-3, ¶¶ 14-15.
16 IP-Output Waiver Order, 27 FCC Rcd at 14882, ¶ 14.
17 The DLNA CVP-2 guidelines that the industry plans to use were released on March 18, 2014. Press Release,
Digital Living Network Alliance, The Digital Living Network Alliance Releases CVP-2 Guidelines for Viewing
Subscription TV Content on Multiple Home Devices (March 18, 2014), available at
http://www.dlna.org/docs/default-source/press-releases/the-digital-living-network-alliance-releases-cvp-2-
guidelines-for-viewing-subscription-tv-content-on-multiple-home-devices.pdf?sfvrsn=4. DLNA expects that “the
DLNA CVP-2 Certification program will be complete and ready to begin certification of products to the DLNA
CVP-2 Guidelines in September 2014,” and that “products may complete certification in the fourth quarter of 2014.”
Letter from Donna Moore, Executive Director, Digital Living Network Alliance, to Marlene H. Dortch, Secretary,
Federal Communications Commission, at 2 (February 14, 2014). See also NCTA Comments at 2-4; Verizon
Comments at 1-4.
18 IP-Output Waiver Order, 27 FCC Rcd at 14882-3, ¶ 15.
19 AllVid Tech Company Alliance Comments at 1; CEA Comments at 1; NCTA Comments at 6; Verizon Comments
at 1-2.
20 Compare IP-Output Waiver Order, 27 FCC Rcd at 14882-3, ¶ 15 with Letter from Donna Moore, Executive
Director, Digital Living Network Alliance, to Marlene H. Dortch, Secretary, Federal Communications Commission,
at 2 (February 14, 2014). See also Verizon Comments at 2-3; NCTA Comments at 2.
21 IP-Output Waiver Order, 27 FCC Rcd at 14884, ¶ 17 (granting small cable operators waiver for three months
more than others).
22 IP-Output Waiver Order, 27 FCC Rcd at 14884, ¶ 17.
23 ACA Reply at 1-2.
24 47 C.F.R. § 76.901(e).
3

Federal Communications Commission
DA 14-461

IV.

ORDERING CLAUSES

6.
Accordingly,

IT IS ORDERED

, pursuant to Section 629(c) of the Communications Act
of 1934, as amended, 47 U.S.C. § 549(c), and Sections 1.3 and 76.7 of the Commission’s rules, 47 C.F.R.
§§ 1.3 and 76.7, that TiVo Inc.’s request for waiver of Section 76.640(b)(4)(iii)

IS GRANTED

to the
extent described above, effective for all cable operators with more than 400,000 subscribers until June 1,
2015.
7.

IT IS FURTHER ORDERED

, pursuant to Section 629(c) of the Communications Act
of 1934, as amended, 47 U.S.C. § 549(c), and Sections 1.3 and 76.7 of the Commission’s rules, 47 C.F.R.
§§ 1.3 and 76.7, that waiver of Section 76.640(b)(4)(iii)

IS GRANTED

to the extent described above,
effective for all cable operators with 400,000 or fewer subscribers until September 1, 2015.
8.
This action is taken by the Chief, Media Bureau, pursuant to authority delegated by
Section 0.283 of the Commission’s rules.25
FEDERAL COMMUNICATIONS COMMISSION
William T. Lake
Chief, Media Bureau


2547 C.F.R. § 0.283.
4

Note: We are currently transitioning our documents into web compatible formats for easier reading. We have done our best to supply this content to you in a presentable form, but there may be some formatting issues while we improve the technology. The original version of the document is available as a PDF, Word Document, or as plain text.

close
FCC

You are leaving the FCC website

You are about to leave the FCC website and visit a third-party, non-governmental website that the FCC does not maintain or control. The FCC does not endorse any product or service, and is not responsible for, nor can it guarantee the validity or timeliness of the content on the page you are about to visit. Additionally, the privacy policies of this third-party page may differ from those of the FCC.