November 28, 2012
DA 12-1902
In Reply Refer to:
1800B3-PPD
Released: November 28, 2012
Dan J. Alpert, Esq.
2120 N. 21st Rd.
Arlington, VA 22201
In re:
KAHA(FM), Olney, TX 
Facility ID No. 164193
South Texas FM Investments, LLC
File No. BLH-20100407ACP
KXME(FM), Wellington, TX 
Facility ID No. 164197
South Texas FM Investments, LLC
File No. BLH-20100407ACO

Petitions for Reconsideration

Dear Counsel:
We have before us two separate Petitions for Reconsideration (“Petitions”), filed by you 
(“Counsel”) on behalf of South Texas FM Investments, LLC (“STI”).  The first Petition for 
Reconsideration (“KAHA Petition”) seek reconsideration of a February 24, 2011 staff letter in which the 
Media Bureau (“Bureau”) dismissed STI’s Application for License (“KAHA License Application”) to 
cover Construction Permit BNPH-20050103AFZ, as modified by BMPH-20100330AEW (“KAHA CP”).  
The other Petition for Reconsideration (“KXME Petition”) seek reconsideration also of a February 24, 
2011 staff letter in which the Bureau dismissed STI’s Applications for License (“KXME License 
Application”) to cover Construction Permit BNPH-20050103ABG, as modified by BMPH-
20100330AEV (“KXME CP”).  Both License Applications were submitted by STI, the permittee of the 
new Stations KAHA, channel 282A at Olney, Texas and KXME, channel 253A at Wellington, Texas.  
For the reasons set forth below, we dismiss STI’s Petitions.1

Background.  

KAHA(FM), Olney, TX.  Pursuant to the KAHA CP’s terms, STI was required to 
finish construction of the station and file a license application to cover the KAHA CP by April 7, 2010.  
STI filed the KAHA License Application on April 7, 2010.  
 
 
1 STI also filed Petitions for Reconsideration to reinstate the construction permits.  In seeking reinstatement of the 
construction permits, STI simply referenced its Petitions regarding the dismissal of the License Applications.  Our 
decision to affirm staff’s dismissal of the License Applications means STI’s construction permits automatically 
expire by operation of law.

On June 21, 2010, Commission staff returned the KAHA License Application as unacceptable for 
filing pursuant to Section 73.3564(a)(1) of the Commission’s rules.2 Staff deemed the filing unacceptable 
because STI failed to submit the required directional antenna proof of performance, antenna installation 
certifications, and radiofrequency radio (“RFR”) measurements required by the Special Operating 
Conditions on the KAHA CP and failed to construct a main studio prior to filing the license application.  
Staff also denied STI’s associated request for waiver of the main studio rule and request for program test 
authority. 
On July 26, 2010, STI submitted a Petition for Reconsideration of the staff’s dismissal of the 
KAHA License Application, a request for reinstatement of the KAHA License Application nunc pro tunc
and an amendment to the KAHA License Application purportedly containing the items required by the 
Special Operating Conditions on the CP.  Commission staff promptly reviewed the petition and the 
amendment to the KAHA License Application.  Staff was unable to act on the KAHA License 
Application because the amendment submitted by STI did not contain all of the items required by the 
KAHA CP.  Accordingly, staff contacted Counsel by telephone and requested an additional amendment, 
containing the required RFR measurements and a detailed description of the access restrictions in place at 
the KAHA transmitter site.
On August 18, 2010, STI submitted a second amendment to the KAHA License Application.  
Commission staff promptly reviewed the amendment and found the data submitted still was not sufficient 
to assess compliance with all of the Special Operating Conditions on the KAHA CP and the 
Commission’s Rules.  Once again, staff contacted Counsel by telephone shortly after receipt of the 
application amendment and requested another amendment to the KAHA License Application containing 
the following items:
1. RFR measurements taken with the station operating at full power, i.e. 1.00 kilowatt effective 
radiated power; and
2. Photographs showing the locations of the authorized tower and the fence surrounding it that is 
required to prevent casual or inadvertent public access to areas in the vicinity of the KAHA 
transmitting facilities where RFR levels are predicted to exceed general population/uncontrolled 
maximum permissible exposure limits.
Thereafter, on November 9, 2010, staff wrote Counsel a letter again asking for the RFR 
measurements and photographs, with a deadline of November 30, 2010 to amend the application. On 
November 12, 2010 and November 30, 2010, STI filed two more amendments providing additional 
technical data, including RFR measurements taken at full authorized power.  Staff’s review of those 
amendments showed STI did not submit the required photographs showing the location of the KAHA 
transmitting facilitates and the surrounding fence in either of the application amendments.  Staff’s review 
also showed that the field strength meter used to take the reported RFR measurements was not of 
sufficient verifiable accuracy.  
Subsequently, in early January, staff contacted Counsel by telephone to again request transmitter 
site photographs and full-power RFR measurements taken using an accurate and verifiable RFR field 
strength meter.  Staff specified a January 30, 2011 deadline for providing the requested information.  On 
February 3, 2011, Counsel requested an extension of time, for “no later than during the last week of 
February,” to amend the KAHA License Application to provide the required transmitter site photographs 
and RFR measurements.  Staff did not act on that extension request.
 
 
See 47 C.F.R §73.3564(a)(1) (“Applications that are not substantially complete will not be considered and will be 
returned to the applicant.”).
2

As of February 24, 2011, STI had not submitted an acceptable amendment to the KAHA License 
Application containing the required information, despite staff’s repeated requests and STI’s repeated 
promises to do so.  Consequently, pursuant to Sections 0.283 and 73.3568(a)(1) of the Commission’s 
Rules, the Bureau dismissed the KAHA License Application for failure to prosecute.3 As a result, the 
KAHA CP expired by operation of law on April 7, 2010, and the call sign for Station KAHA was deleted.
On March 17, 2011, STI filed the KAHA Petition and on March 18, 2011, STI filed another 
amendment with additional measurements and photos, purporting to provide the information initially 
requested by staff.  STI seeks reinstatement and grant of the KAHA License Application.  
KXME(FM), Wellington, TX.  Pursuant to the KXME CP’s terms, STI was required to finish 
construction of the station and file a license application by April 7, 2010.  STI filed the KXME License 
Application on April 7, 2010.  
On May 14, 2010, Commission staff returned the KXME License Application as unacceptable for 
filing pursuant to Section 73.3564(a)(1) of the Commission’s rules.4 Staff deemed the filing unacceptable 
because STI failed to submit the required directional antenna proof of performance, antenna installation 
certifications, and RFR measurements required by the Special Operating Conditions on the KXME CP 
and failed to construct a main studio prior to filing the license application.  The staff also denied STI’s 
associated request for waiver of the main studio rule and request for program test authority. 
On June 17, 2010, STI submitted a Petition for Reconsideration of the staff’s dismissal of the 
KXME License Application, a request for reinstatement of the KXME License Application nunc pro tunc
and an amendment to the KXME License Application purportedly containing the items required by the 
Special Operating Conditions on the CP.  Commission staff promptly reviewed the petition and the 
amendment to the KXME License Application.  On July 21, 2010, staff granted the petition and reinstated 
the KXME License Application.  However, staff was unable to act on the KXME License Application 
because the amendment submitted by STI did not contain all of the items required by the KXME CP.  
Accordingly, the staff contacted Counsel by telephone and requested an additional amendment to the 
KXME License Application containing the required RFR measurements and a detailed description of the 
access restrictions in place at the KXME transmitter site.
On July 26, 2010, STI submitted a second amendment to the KXME License Application.  
Commission staff promptly reviewed the amendment and found the data submitted still was not sufficient 
to assess compliance with all of the Special Operating Conditions on the KXME CP and the 
Commission’s Rules.  On November 9, 2010, staff issued a letter providing KXME another opportunity 
to submit the following items:
1. RFR measurements taken with the station operating at full power, i.e. 1.00 kilowatt effective 
radiated power; and
2. Photographs showing the locations of the authorized tower and the fence surrounding it that is 
required to prevent casual or inadvertent public access to areas in the vicinity of the KXME 
transmitting facilities where RFR levels are predicted to exceed general population/uncontrolled 
maximum permissible exposure limits.
 
 
See 47 C.F.R. §0.283 (conferring delegated authority to Media Bureau to process applications) and 47 C.F.R. 
§73.3568(a)(1) (failure to prosecute an application is cause for dismissal).
See 47 C.F.R §73.3564(a)(1).
3

On November 12, 2010 and November 30, 2010, STI filed two more amendments providing 
additional technical data, including RFR measurements taken at full authorized power.  Staff’s review of 
those amendments showed STI did not submit the required photographs showing the location of the 
KXME transmitting facilitates and the surrounding fence in either of the application amendments.  Staff’s 
review also showed that the field strength meter used to take the reported RFR measurements was not of 
sufficient verifiable accuracy.  
Subsequently, in early January, staff contacted Counsel by telephone to once again request 
transmitter site photographs and full-power RFR measurements taken using an accurate and verifiable 
RFR field strength meter.  Staff specified a January 30, 2011 deadline for providing the requested 
information.  On February 3, 2011, Counsel requested an extension of time, for “no later than during the 
last week of February,” to amend the KXME License Application to provide the required transmitter site 
photographs and RFR measurements.  Staff did not act on that extension request. 
As of February 24, 2011, STI had not submitted an acceptable amendment to the KXME License 
Application containing the required information, despite staff’s repeated requests and STI’s repeated 
promises to do so.  Consequently, pursuant to Sections 0.283 and 73.3568(a)(1) of the Commission’s 
Rules, the Bureau dismissed the KXME License Application for failure to prosecute.5 As a result, the 
KXME CP expired by operation of law on April 7, 2010, and the call sign for Station KXME was deleted.
On March 17, 2011, STI filed the KXME Petition and on March 18, 2011, STI filed another 
amendment with additional measurements and photos, purporting to provide the information initially 
requested by staff.  STI seeks reinstatement and grant of the KXME License Application.  

Discussion. 

In both Petitions, STI argues reconsideration is appropriate because staff may have 
been unaware of STI’s request for additional time to submit the required information by the end of 
February 2011.  Because STI did not receive a response to its extension request, it presumed the request 
had been granted, which would have allowed STI until the end of February to submit the requested 
measurements and photographs.  STI claims now it was working to get the Commission the requested 
information by March 2011, when “unexpectedly, without warning” the Commission dismissed both 
license applications on February 24, 2011.  
STI also seeks reconsideration because it was in contact with staff.  STI claims the Commission 
incorrectly dismissed the KAHA and KXME License Applications for failure to prosecute because STI 
had been in regular contact with staff and had filed numerous amendments, evidencing responsiveness to 
staff’s requests and its intent to prosecute both license applications.
The Commission will consider a Petition for Reconsideration only when the petitioner shows 
either a material error in the Commission’s original order or raises changed circumstances or unknown 
additional facts not known or existing at the time of petitioner’s last opportunity to present such matters.6  
As discussed below, STI has not met this test.
 
 
See 47 C.F.R. §0.283 and 47 C.F.R. §73.3568(a)(1).
See 47 C.F.R. § 1.106, WWIZ, Inc., Memorandum Opinion and Order, 37 FCC 685, 686 (1964), aff’d sub nom., 
Lorain Journal Co. v. FCC
, 351 F.2d 824 (D.C. Cir. 1965), cert. denied, 387 U.S. 967 (1966), and National 
Association of Broadcasters
, Memorandum Opinion and Order, 18 FCC Rcd 24414, 24415 (2003).  It is also 
appropriate to consider new facts not previously presented when such consideration is required in the public interest.  
See 47 C.F.R. § 1.106(c)(2).
4

In both the KAHA and KXME Petitions, STI appears to be relying on its request for an extension 
of time as evidence of either new circumstances or error by the Commission.  STI first presumed the 
extension had been granted and now presumes staff may not have been aware of the extension request.  
However, it was STI’s error to rely on its own presumptions.  Section 1.46 of the Commission’s rules 
clearly states it is our policy that extensions of time may not be routinely granted.7 Because neither of the 
extensions was granted, STI was required to comply with the January 30, 2011 deadline.8  
Moreover, STI argues since it had been in constant contact with the Commission, it was clear STI 
intended to prosecute the applications. This argument ignores the fact that staff provided STI numerous 
opportunities to provide the requested information over the course of almost one year.  At some point, 
staff had to resolve the pending license applications and could not indefinitely wait for STI’s compliance 
with the Special Operating Conditions on the KAHA and KXME CPs.  Ultimately, to resolve the pending 
license applications, staff gave STI a final opportunity to file all the required information by January 30, 
2011.  STI provides no adequate explanation for its failure to comply with the numerous requests and 
opportunities to submit the requested information by the specified deadline.  
STI has not presented any new facts or raised any material error in the Commission’s dismissal of 
the KAHA and KXME License Applications.  We cannot condone STI’s failure to provide the 
appropriate information at the required time.  Consequently, staff action was proper in dismissing the 
license applications.  Accordingly, we will deny STI’s KAHA and KXME Petitions for Reconsideration.  
Finally, we reject STI’s proffered amendment to its KAHA and KXME License Applications. As 
discussed above, the applications were dismissed because of STI’s failure to provide information
repeatedly requested by staff.  Accordingly, STI cannot proffer, after the fact, the requested information
and claim it is entitled to reinstatement nunc pro tunc of its applications.9 Therefore, we will not consider 
STI’s latest amendments of March 18, 2011, which purportedly produced the requested information.

Conclusion.  

Accordingly, IT IS ORDERED the Petitions for Reconsideration filed by South 
Texas FM Investments, LLC on March 17, 2011, ARE DENIED.  Construction Permit BMPH-
20100330AEW for Station KAHA, Olney, Texas and Construction Permit BMPH-20100330AEV for 
Station KXME, Wellington, Texas EXPIRED BY OPERATION OF LAW on April 7, 2010, without 
further action by the Commission.
Sincerely,
Peter H. Doyle
Chief, Audio Division
Media Bureau
 
 
See 47 C.F.R. § 1.46; Royce International Broadcasting Co., 23 FCC Rcd 9010 (2008).
8 STI requested an extension until “no later than during the last week of February” to file the amendments to the 
KAHA and KXME License Applications.  Thus, even if STI’s presumption was correct, it still failed to comply with 
its own proposed filing deadline.    
See Canyon Area Residents, Memorandum Opinion and Order, 14 FCC Rcd 8152, 8154 (1999), quoting Colorado 
Radio Corp. v. FCC
, 118 F. 2d 24, 26 (D.C. Cir. 1941).  The Commission has stated before, “[w]e cannot allow a 
party to ‘sit back and hope that a decision will be in its favor and, when it isn’t, to parry with an offer of more 
evidence. No judging process in any branch of government could operate efficiently or accurately if such a 
procedure were allowed.’” 
5

Edoc Internal Id: 
317600
Released On: 
Tue, 2012-11-27 19:00
Published On: 
November 28 2012
Edoc ID: 
DA-12-1902

close
FCC

You are leaving the FCC website

You are about to leave the FCC website and visit a third-party, non-governmental website that the FCC does not maintain or control. The FCC does not endorse any product or service, and is not responsible for, nor can it guarantee the validity or timeliness of the content on the page you are about to visit. Additionally, the privacy policies of this third-party page may differ from those of the FCC.