Temporary Waiver to Permit PLMR Conditional Authority Above 470 MHz

Download Options

Released: September 26, 2013

Federal Communications Commission

DA 13-1989

Before the

Federal Communications Commission

Washington, D.C. 20554

In the Matter of
)
)
ENTERPRISE WIRELESS ALLIANCE
)
)
Request for Temporary Waiver Part 90
)
Conditional Licensing Authority Above 470 MHz
)

ORDER

Adopted: September 26, 2013

Released: September 26, 2013

By the Deputy Chief, Mobility Division, Wireless Telecommunications Bureau:
1.
Introduction. We have before us the request of the Enterprise Wireless Alliance (EWA)
for a temporary waiver of Section 90.159(b) of the Commission's Rules1 to permit applicants for new or
modified stations in the 470-512 MHz, 806-824/851-866 MHz, and 896-901/935-940 MHz bands to
operate while the applications are pending.2 We grant the request as set forth below.
2.
Background. Pursuant to Section 90.159(b), most applicants proposing to operate a new
private land mobile radio (PLMR) station or modify an existing PLMR station below 470 MHz that are
required to include a showing of frequency coordination are permitted to operate the proposed station
during the pendency of the application for a period of up to 180 days, beginning ten days after the
application is submitted to the Commission.3 This conditional authority is not available for applicants in
the PLMR frequency bands above 470 MHz.
3.
EWA notes that the Commission's January 1, 2013 PLMR narrowbanding deadline
triggered the filing of a large number of Part 90 applications in late 2012 and into 2013, resulting in
notably longer processing times for non-Public Safety Pool applications.4 EWA contends that the
limitation in Section 90.159(b) to applications below 470 MHz "creates the anomalous situation whereby,
for example, a licensee proposing to upgrade from analog to digital equipment, which requires a
modification of the emission designator, can deploy its new technology 10 business days after its below-


1 See 47 C.F.R. 90.159(b).
2 See Letter dated June 21, 2013 from Mark E. Crosby, President/CEO, EWA to Ruth Milkman, Chief, Wireless
Telecommunications Bureau (Waiver Request). The Waiver Request supersedes a previous request from EWA that
the Wireless Telecommunications Bureau prioritize the processing of applications above 470 MHz. See Letter dated
June 4, 2013 from Mark E. Crosby, President/CEO, EWA to Ruth Milkman, Chief, Wireless Telecommunications
Bureau (Prioritization Request).
3 See 47 C.F.R. 90.159(b), (b)(6). This conditional authority applies only to applications that meet the following
requirements: the proposed station location is south of Line A and west of Line C; the proposed antenna structure
has previously been determined by the Federal Aviation Administration to pose no hazard to aviation safety, or the
proposed structure height does not exceed 6.1 meters above ground level or above an existing man-made structure;
grant of the application does not require a waiver of the Commission's rules; the proposed facility will not have a
significant environmental effect; and the proposed station is not in a quiet zone. 47 C.F.R. 90.159(b)(1)-(5).
4 See Prioritization Request at 1; Waiver Request at 1 & n.2.

Federal Communications Commission

DA 13-1989

470 MHz application is filed, yet must wait many months if the system is in the 470-512 MHz, 800 MHz,
or 900 MHz frequency bands."5
4.
EWA believes that conditional licensing is appropriate for all Part 90 bands, and intends
to file a petition requesting that the Commission amend its rules to permit this flexibility above 470
MHz.6 In the interim, it requests a temporary waiver of the below-470 MHz limitation in Section
90.159(b). Specifically, EWA requests a waiver to grant conditional authority for above-470 MHz
applications filed with the Wireless Telecommunications Bureau (WTB) on or before December 31, 2013
that meet all of the other requirements and conditions of Section 90.159(b).7
5.
Discussion. To obtain a waiver of the Commission's Rules, a petitioner must
demonstrate either that (i) the underlying purpose of the rule(s) would not be served or would be
frustrated by application to the present case, and that a grant of the waiver would be in the public
interest;8 or (ii) in view of unique or unusual factual circumstances of the instant case, application of the
rule(s) would be inequitable, unduly burdensome, or contrary to the public interest or the applicant has no
reasonable alternative.9 Based on the record before us, we conclude that EWA has presented sufficient
facts to meet the standard for grant of a waiver. We agree with EWA that the large number of
narrowbanding-related applications and the attendant temporary increase in processing time for all
WTB applications is a unique or unusual factual circumstance for which waiver relief is
appropriate.10 We also agree that, under the circumstances, restricting conditional authority to
applications involving frequencies below 470 MHz during this period would be inequitable and
unduly burdensome to applicants that could not have anticipated this increased processing time.11
Finally, we conclude that temporarily allowing above-470 MHz PLMR applicants to initiate service
consistent with the requirements of Section 90.159(b) would serve the public interest by permitting
the more timely deployment of systems that serve many parties' communications needs.
6.
Consequently, we grant EWA's request to temporarily waive Section 90.159(b) for
applications in the 470-512 MHz, 806-824/851-866 MHz, and 896-901/935-940 MHz bands with WTB
radio service codes12 filed on or before December 31, 2013 (including applications that are currently
pending). We grant the waiver only for PLMR applications filed on or before that date because we expect
processing times to return to normal by the time that applications filed thereafter are processed. This
waiver applies only to such applications that meet all of the requirements of Section 90.159(b) other than
the below-470 MHz limitation. The waiver does not apply to public safety applicants or licenses.


5 See Waiver Request at 1.
6 See Prioritization Request at 1. When the Commission enacted the rule granting conditional authority below 470
MHz, it stated that it was being conservative in the implementation of conditional authority, and could consider
expanding the concept in the future if experience demonstrated that such action was appropriate. See Amendment of
Part 90 of the Commission's Rules to Implement a Conditional Authorization Procedure for Proposed Private Land
Mobile Radio Service Stations, Report and Order, PR Docket No. 88-567, 4 FCC Rcd 8280, 8283 25 (1989).
7 See Waiver Request at 1-2.
8 47 C.F.R. 1.925(b)(3)(i).
9 47 C.F.R. 1.925(b)(3)(ii).
10 See Waiver Request at 2.
11 Id.
12 See http://wireless.fcc.gov/uls/index.htm?job=radio_services.
2

Federal Communications Commission

DA 13-1989

7.
We remind applicants that frequency coordination recommendations are advisory in
character and not an assurance that the Commission will grant the requested license.13 Conditional
authority does not prejudice any action the Commission may take on the application, and may be
modified or canceled by the Commission at any time.14 The applicant assumes all risk associated with
operation under conditional authority15 and should be cautious in purchasing radio equipment prior to
obtaining a valid permanent authorization from the Commission.16
8.
Conclusion and Ordering Clauses. Accordingly, IT IS ORDERED pursuant to Section
4(i) of the Communications Act of 1934, as amended, 47 U.S.C. 154(i), and Section 1.925(b)(3) of the
Commission's Rules, 47 C.F.R. 1.925(b)(3), that the Request for Temporary Waiver filed by the
Enterprise Wireless Alliance on June 21, 2013 IS GRANTED to the extent set forth in paragraph 6.
9.
This action is taken under delegated authority pursuant to Sections 0.131 and 0.331 of the
Commission's rules, 47 C.F.R. 0.131, 0.331.
FEDERAL COMMUNICATIONS COMMISSION
Scot Stone
Deputy Chief, Mobility Division
Wireless Telecommunications Bureau


13 47 C.F.R. 90.175(h).
14 47 C.F.R. 90.159(d).
15 Id.
16 47 C.F.R. 90.175(h).
3

Note: We are currently transitioning our documents into web compatible formats for easier reading. We have done our best to supply this content to you in a presentable form, but there may be some formatting issues while we improve the technology. The original version of the document is available as a PDF, Word Document, or as plain text.

close
FCC

You are leaving the FCC website

You are about to leave the FCC website and visit a third-party, non-governmental website that the FCC does not maintain or control. The FCC does not endorse any product or service, and is not responsible for, nor can it guarantee the validity or timeliness of the content on the page you are about to visit. Additionally, the privacy policies of this third-party page may differ from those of the FCC.