Waiver of Cost Estimate Deadline

Download Options

Released: November 26, 2013
image01-00.jpg612x792

Federal Communications Commission

DA 13-2269

Before the

Federal Communications Commission

Washington, D.C. 20554

In the Matter of

)

)

Improving Public Safety Communications

)

in the 800 MHz Band

)

Docket No. 02-55

)

Gilcomm, LLC.

)

ORDER

Adopted: November 26, 2013

Released: November 26, 2013

By the Deputy Chief, Policy and Licensing Division, Public Safety and Homeland Security Bureau

I.

INTRODUCTION

1.

Under consideration is the “Request for Waiver Related to Commission November 20, 2013

Deadline for Submission of Estimates” (Request) filed by Gilcomm, LLC (Gilcomm) seeking an

extension of time within which to file a rebanding cost proposal with Sprint Corporation (Sprint) as part

of the Commission’s 800 MHz band reconfiguration initiative.1

II.

DISCUSSION

2.

Gilcomm operates an EDACS 800 MHz trunked network and an EF Johnson 800 MHz LTR

network in the Bakersfield, California area.2 Gilcom submits that 21 of its authorized channels must be

rebanded.3 It states that a substantial amount of cost data has been collected and a partial Transition Plan

has been drafted.4 However, given the mix of EDACS and LTR operations, Gilcomm submits that

additional time to complete estimates will be required as some issues have arisen that must be resolved to

assure that the estimates are accurate.5 Gilcomm requests a short extension of time until December 2,

2013 to submit its cost estimate to Sprint.6

III. DECISION

3.

Section 1.46 of the Commission’s rules provides “It is the policy of the Commission that

extensions of time shall not be routinely granted.”7 The import of that rule is especially relevant to 800

1 Request for Waiver Related to Commission November 20, 2013 Deadline for Submission of Estimates submitted

by Gilcomm, LLC, (Nov. 20, 2013) re WNNJ606.

2

Id.

3

Id.

4

Id.

5

Id.

6

Id.

7 47 C.F.R. § 1.46.

1

image02-00.jpg612x792

Federal Communications Commission

DA 13-2269

MHz rebanding where delay in rebanding by one licensee can cause a “domino effect” delay in the

rebanding efforts of other licensees that have met the Commission’s 800 MHz band reconfiguration

deadlines, with a consequent delay of the overall program. We therefore afford a high degree of scrutiny

to the reasons licensees advance for extensions of time.8

4.

In the instant matter, the extension of time requested is relatively modest and it is apparent

that the licensee has exercised diligence in drafting a partial Transition Plan and seeking to ensure the

accuracy of its costs estimates. We therefore are granting the requested extension, with the caveat to the

licensee that, upon submission of the cost proposal, it must diligently pursue the negotiation process with

Sprint and timely conclude an FRA.

IV. ORDERING CLAUSES

5.

Accordingly, IT IS ORDERED that the Request for Waiver Related to Commission

November 20, 2013 Deadline for Submission of Estimates filed by Gilcomm, LLC, IS

GRANTED.

6.

IT IS FURTHER ORDERED that Gilcomm, LLC, SHALL SUBMIT to Sprint Corporation, a

cost proposal for reconfiguration of 800 MHz facilities, call sign WNNJ606, by December 2, 2013.

7.

This action is taken under delegated authority pursuant to Sections 0.191 and 0.392 of the

Commission’s rules, 47 C.F.R. §§ 0.191, 0.392.

FEDERAL COMMUNICATIONS COMMISSION

Michael J. Wilhelm

Deputy Chief, Policy and Licensing Division

Public Safety and Homeland Security Bureau

8 See Regents of the University of California, WT Docket 02-55, Order, DA 13-2234, (PSHSB rel. Nov. 21, 2013).

2

Note: We are currently transitioning our documents into web compatible formats for easier reading. We have done our best to supply this content to you in a presentable form, but there may be some formatting issues while we improve the technology. The original version of the document is available as a PDF, Word Document, or as plain text.

close
FCC

You are leaving the FCC website

You are about to leave the FCC website and visit a third-party, non-governmental website that the FCC does not maintain or control. The FCC does not endorse any product or service, and is not responsible for, nor can it guarantee the validity or timeliness of the content on the page you are about to visit. Additionally, the privacy policies of this third-party page may differ from those of the FCC.