Acceleration of Broadband Deployment: Expanding the Reach and Reducing the Cost of Broadband Deployment by Improving Policies Regarding Government Rights of Way and Wireless Facilities Siting

Download Options

Released: May 4, 2011

Federal Communications Commission

FCC 11-51

Before the

Federal Communications Commission

Washington, D.C. 20554

In the Matter of
)
)
Acceleration of Broadband Deployment:
)
WC Docket No. 11-59
Expanding the Reach and Reducing the Cost of
)
Broadband Deployment by Improving Policies
)
Regarding Public Rights of Way and Wireless
)
Facilities Siting
)

NOTICE OF INQUIRY

Adopted: April 7, 2011

Released: April 7, 2011

Comment Date: 60 days after Federal Register publication
Reply Comment Date: 105 days after Federal Register publication

By the Commission:

I.

INTRODUCTION

1.
This Notice of Inquiry (Notice) concerns key challenges and best practices in expanding the
reach and reducing the cost of broadband deployment by improving government policies for access to
rights of way and wireless facilities siting. As such it is a leading element of the Commission's
Broadband Acceleration Initiative. Increasing broadband deployment throughout the nation is one of the
great infrastructure challenges of our time. Communications technology and services--particularly
broadband--are critical to our country's economic success in the twenty-first century. Broadband can
drive local and national economic growth, as well as improve education, healthcare, and energy
efficiency.
2.
Congress has directed this "Commission and each State commission with regulatory
jurisdiction over telecommunications services [to] encourage the deployment on a reasonable and timely
basis of [broadband] to all Americans" by working to "remove barriers to infrastructure investment" in a
manner consistent with the public interest, convenience, and necessity.1 Accordingly, in this proceeding
we seek to work with stakeholders including state and local governments, other federal agencies, Tribal
governments, consumer advocates, and the private sector to identify means of improving rights of way
policies and wireless facilities siting requirements. By working together on these issues, we can reduce
the costs and time required for broadband deployment, both fixed and mobile, which will help unleash
private investment in infrastructure, increase efficient use of scarce public resources (including


1 47 U.S.C. 1302(a) (2010). In this Notice, we use the term "broadband" interchangeably with "advanced
telecommunications capability" as used in section 1302. We note that section 706 of the Telecommunications Act
of 1996, Pub. L. No. 104-104, 706, 110 Stat. 56, 153 (the 1996 Telecommunications Act), as amended in relevant
part by the Broadband Data Improvement Act, Pub. L. No. 110-385, 122 Stat. 4096 (2008) (BDIA), is now codified
in Title 47, Chapter 12 of the United States Code. See 47 U.S.C. 1301 et seq.

Federal Communications Commission

FCC 11-51
spectrum),2 and increase broadband adoption.
3.
Providing broadband service requires the deployment and use of varied and physically
dispersed communications infrastructure, including cables, antennas, poles, towers, and a variety of
electronic equipment. This equipment is placed in public and private rights of way, such as in roads and
railbeds or on towers and building roof tops.3 Access to public rights of way, tower sites, and buildings is
governed by federal, state, local, or Tribal4 requirements depending on the location.5 What type of
facility is needed depends on the particular type of infrastructure being deployed.6
4.
Policies for managing rights of way and siting wireless facilities, including the procedures
and costs for acquiring permission to build, affect how long it takes and how much it costs to deploy
broadband.7 These issues are particularly complex because of the important and potentially competing
interests that must be balanced, and the variety of different jurisdictions involved. Particular


2 We note that access to poles, towers, and other infrastructure is essential to "spatial reuse" of our nation's spectrum
resource.
3 Both new construction of wireless antenna structures and the availability of existing structures for purposes of
collocating additional antennas have been, and will continue to be, integral to wireless build-out. These structures
provide opportunities for future broadband use, for new technologies such as LTE or WiMax, and for new entrants
into the broadband market.
4 Tribal governments and individual owners or interest holders have authority concerning rights of way within their
Native Nations and their individually owned Indian lands, respectively, wherein their consent and federal authority
is required. The Department of Interior's Bureau of Indian Affairs also plays a critical role in the rights of way
processes for lands held by the United States in trust for a Tribe, for lands to which title is held by the Tribe but are
also subject to federal restrictions against alienation and encumbrance, and trust or trust-restricted lands individually
owned by members of federally recognized Tribes. See 25 C.F.R. 169, et seq. (Rights-Of-Way Over Indian
Lands). Federal rules, in conjunction with the special legal trust status of Tribal and individually owned Indian
lands, create application and review processes designed to reverse the historical methods by which Tribes and their
members lost their lands, and instead preserve and efficiently develop these lands in coordination with the Tribal
trustee. See 25 C.F.R. 169.26 (telephone and telegraph lines; radio, television, and other communications
facilities).
5 Public rights of way are owned and controlled by a number of different government entities, including cities,
towns, counties, states, and a number of federal government entities. In addition, telecommunications carriers, ,
railroads, utilities, and other private entities own or control private rights of way that are used for broadband and
other communications facilities.
6 For example, wireline transmission equipment, such as fiber optic cables, frequently are buried in underground
conduits or attached to poles in public rights of way. Wireless equipment, such as antennas, can often be attached to
existing infrastructure such as utility poles, water towers, billboards, and buildings, as well as to communications
towers, both within and outside of established rights of way. See generally Nationwide Programmatic Agreement for
the Collocation of Wireless Antennas
, 16 FCC Rcd 5574 (Wireless Tel. Bur. 2001) (Collocation Agreement) and
Fact Sheet (January 10, 2002).
7 The wireless industry's need to site facilities is significant and growing. According to CTIA, the total number of
cell sites in use by CTIA's members was 253,086 as of December 31, 2010. See CTIA, Year-End 2010 Top-Line
Survey Results
at 10 (2010), available at http://files.ctia.org/pdf/CTIA_Survey_Year_End_2010_Graphics.pdf. In
addition, the Rural Broadband Report concluded that, in order to achieve ubiquitous mobile broadband coverage in
the U.S., approximately 16,000 new towers will need to be constructed, disproportionately in rural areas. See
BRINGING BROADBAND TO RURAL AMERICAN: REPORT ON A RURAL BROADBAND STRATEGY, 158 (May 22, 2009),
available at http://hraunfoss.fcc.gov/edocs_public/attachmatch/DOC-291012A1.doc. However, evidence suggests
that this figure may have understated the growing need for new wireless infrastructure. See Presentation by Nadine
Manjaro, ABI Research, PCIA Wireless Infrastructure Show Debrief, at 2009 Wireless Infrastructure Show, Oct. 1,
2009, available at http://www.rcrwireless.com/assets/pdf/PCIA_Wireless2009_Debrief.pdf.
2

Federal Communications Commission

FCC 11-51
administrative requirements often reflect significant public interest objectives of the government entities
involved, such as ensuring public safety and maintaining roadways and other critical community
infrastructure. Further, access to unique rights of way, tower sites, and other facilities suitable for the
deployment of communications facilities can have scarcity value or quasi-monopoly characteristics given
the need for access by infrastructure providers8 and the lack of reasonable alternatives in many cases.9
Additionally, fragmented property ownership creates a patchwork of requirements that providers must
satisfy on a piecemeal basis. For example, a single broadband deployment project may need to access
rights of way owned and regulated by multiple government entities--the federal government, states, and
multiple localities, as well as private rights of way such as those along railroads.10 Obtaining access to
rights of way on fair and reasonable terms, and through a predictable process, is critical for all
infrastructure providers.
5.
The Commission, the National Telecommunications and Information Administration
(NTIA), and the National Association of Regulatory Utility Commissioners (NARUC) examined these
issues and potential solutions in the late 1990s and early 2000s and took steps to address these complex
problems. In 2002, NARUC published a study that addressed rights of way practices11 and rates at both
the state and federal level and included a summary of state rights of way legislation, rights of way best
practices, access to public lands, and federal policies to eliminate obstacles to the deployment of
broadband.12 In 2004, the Federal Rights of Way Working Group, led by NTIA, made recommendations
for improving federal rights of way policy and included recommendations for information collection,


8 We use the phrase "infrastructure providers" here to describe both facilities-based service providers (i.e.,
companies that offer communications services over network facilities they own and operate) and other facilities
providers who provide infrastructure to service providers (i.e., entities that build and/or lease facilities to broadband
providers but do not offer such service themselves).
9 Public rights of way are especially critical to the deployment of communications facilities due to their widespread
availability and efficiency for use in deploying communications networks. Indeed, there are relatively few roads or
highways in America that do not have communications infrastructure running over, under, or alongside the roadway.
The limited alternatives that exist for the placement of communications networks are often less efficient or have
other drawbacks. For example, the use of long distance gas pipeline rights of way raises special safety concerns,
and often do not connect population centers as directly as limited access highways. See Petition of the State of
Minnesota for Declaratory Ruling Regarding the Effect of Section 253 on an Agreement To Install Fiber Optic
Wholesale Transport Capacity in State Freeway Rights of Way
, CC Docket No. 98-1, Memorandum Opinion and
Order, 14 FCC Rcd 21697, 21709-12 (1999) (Minnesota Order).
10 Further, different portions of broadband transmission networks often use different types of rights of way. For
example, fiber optic facilities used primarily for long-haul broadband transmission frequently use rights of way
along limited access highways controlled by the states. Such rights of way are also subject to Federal Highway
Administration requirements in the case of federally funded highways. See Opposition of New York State Thruway
Authority, Level 3 Communications, LLC Petition for Declaratory Ruling That Certain Rights of Way Rents
Imposed by the New York State Thruway Authority Are Preempted Under Section 253
, WC Docket No. 09-153, at 3
(dated October 15, 2009). A significant number of states have undertaken projects to facilitate the use of such rights
of way for fiber optic transmission facilities. See generally FHA, RURAL INTERSTATE CORRIDOR COMMUNICATIONS
STUDY REPORT TO STATES (February 2009) available at
http://ops.fhwa.dot.gov/publications/fhwahop09021/fhwahop09021.pdf.
11 For purposes of this proceeding, the term "rights of way practices" includes all procedural and administrative
requirements associated with access to and use of rights of way or wireless facilities siting.
12 See generally NARUC, PROMOTING BROADBAND ACCESS THROUGH PUBLIC RIGHTS OF WAY AND PUBLIC LANDS
(2002).
3

Federal Communications Commission

FCC 11-51
more timely access, and simplification of fee structures for access to federal lands.13
6.
The Commission recently has taken significant steps to reduce barriers to broadband
infrastructure investment. For example, in 2009, the Commission established standards that ensure the
timely processing of wireless tower siting requests while respecting the vital role of local government
authorities in this area.14 The Commission has also taken initial steps to improve pole attachment
practices,15 and today adopts an order that ensures timely and rationally priced access to poles.16 In
addition, the Commission has taken action to increase access to wireless spectrum and reduce barriers to
using spectrum for mobile broadband, as well as facilitating the use of unlicensed "white spaces"
spectrum.17 The Commission previously took steps to "eliminate the unreasonable barriers to entry into
the cable market."18
7.
Last year, the National Broadband Plan (Plan) concluded that the rates, terms, and
conditions for access to rights of way significantly impact broadband deployment.19 The Plan made a
number of recommendations for improving and streamlining access to rights of way. It stated that
"[b]ecause local, state, Tribal and federal governments control access to important rights of way and
facilities, a comprehensive broadband infrastructure policy necessarily requires a coordinated effort
among all levels of government."20 While recognizing differences on certain issues, the Plan found that


13 See generally FEDERAL RIGHTS OF WAY WORKING GROUP, NTIA, IMPROVING RIGHTS OF WAY MANAGEMENT
ACROSS FEDERAL LANDS: A ROADMAP FOR GREATER BROADBAND DEPLOYMENT (2004), available at
http://www.ntia.doc.gov/reports/fedrow/FROWReport_4-23-2004.pdf. The State of California also has identified
rights of way access as a "lengthy, expensive, inconsistent [process,] . . . one of the most significant [barriers] to
broadband deployment[,]"and cited the multiple permitting agencies, varied application forms, and inconsistent
permitting criteria and fees as major contributors to the problem. CALIFORNIA PUBLIC UTILITIES COMMISSION,
BROADBAND DEPLOYMENT IN CALIFORNIA 46, Ch. 6 (2005) available at
http://docs.cpuc.ca.gov/published/comment_decision/43597.htm.
14 See Petition for Declaratory Ruling To Clarify Provisions of Section 332(C)(7)(B) To Ensure Timely Siting
Review and To Preempt Under Section 253 State and Local Ordinances That Classify All Wireless Siting Proposals
as Requiring a Variance
, WT Docket No. 08-165, Declaratory Ruling, 24 FCC Rcd 13994 (2009), recon. denied, 25
FCC Rcd 11157 (2010), appeal pending sub nom., City of Arlington and City of San Antonio v. FCC, Nos. 10-60039
& 10-60805 (5th Cir.).
15 Implementation of Section 224 of the Act; A National Broadband Plan for Our Future, WC Docket No. 07-245,
GN Docket No. 09-51, Order and Further Notice of Proposed Rulemaking, 25 FCC Rcd 11864 (2010).
16 Implementation of Section 224 of the Act; A National Broadband Plan for Our Future, WC Docket No. 07-245,
GN Docket No. 09-51, Report and Order on Reconsideration, FCC 11-50 (April 7, 2011).
17 See Unlicensed Operation in the TV Broadcast Band, ET Docket No. 04-186, Second Memorandum Opinion and
Order, 25 FCC Rcd 18661(2010).
18 See Implementation of Section 621(a)(1) of the Cable Communications Policy Act of 1984 as Amended by the
Cable Television Consumer Protection and Competition Act of 1992
, MB Docket No. 05-311, Report and Order and
Further Notice of Proposed Rulemaking, 22 FCC Rcd 5101, 5103 (2007) (Local Franchising Order) (interpreting
section 621(a)(1), which prohibits local franchising authorities from "unreasonably refusing to award" competitive
cable franchises, and establishing time frames for local action on franchise applications with an interim franchise
deemed granted if the time frames were not met), aff'd sub nom., Alliance for Community Media v. FCC, 529 F.3d
763 (6th Cir. 2008), cert. denied, 129 S. Ct. 2821 (2009).
19 OMNIBUS BROADBAND INITIATIVE, FCC, CONNECTING AMERICA: THE NATIONAL BROADBAND PLAN at 109
(2010) (NATIONAL BROADBAND PLAN).
20 NATIONAL BROADBAND PLAN at 113. The Plan also recognized the important role of the federal government as a
provider of rights of way and other forms of access to federally owned or leased property, and made a number of
recommendations in this regard. Id. at 114-15. It noted that "[t]he federal government is the largest landowner in
(continued....)
4

Federal Communications Commission

FCC 11-51
"nearly all [interested persons] agree that there can and should be better coordination across jurisdictions
on infrastructure issues."21 Accordingly, the Plan recommended that "the FCC . . . develop guidelines for
public rights-of-way policies that will ensure that best practices from state and local government are
applied nationally."22
8.
In February 2011, the Commission announced a Broadband Acceleration Initiative to work
with state, Tribal, and local governments, other federal agencies, and the private sector to identify and
take steps to reduce regulatory and other barriers to broadband deployment.23 The Initiative was
announced at the Broadband Acceleration Conference,24 which brought together leaders from federal,
state, and local governments; broadband providers; telecommunications carriers; tower companies;
equipment suppliers; and utility companies to identify ways to foster broadband deployment.25 The
Conference generated a broad range of ideas for accelerating broadband deployment, many of which are
addressed in this Notice.26
9.
This Notice is intended to update our understanding of current rights of way and wireless
facilities siting policies, assess the extent and impact of challenges related to these matters, and develop a
record on potential solutions to these challenges. This inquiry is a necessary step towards determining
whether there is a need for coordinated national action to improve rights of way and wireless facilities
siting policies, and, if so, what role the Commission should play in conjunction with other stakeholders.
We seek a detailed record of the nature and scope of broadband deployment issues, including both best
practices that have promoted deployment and matters that have resulted in delays. The Commission is
most interested in systemic practices rather than individual or anecdotal situations, which are less suited
for federal policies. So that we might have a factual basis upon which to determine the nature and extent
of any problems, we ask commenters to provide us with information on their experiences, both positive
and negative, related to broadband deployment. In the case of comments that name any state or local
government or Tribal or federal entity as an example of barriers to broadband deployment, we strongly
encourage the party submitting the comments to name the specific government entity it is referring to, and
describe the actions that are specifically cited as an example of a barrier to broadband deployment, as this
(Continued from previous page)


the country[,]" adding that the "General Services Administration (GSA) owns or leases space in 8,600 buildings
nationwide." Id. at 115.
21 Id at 113.
22 Id.
23 See A NATIONAL STRATEGY: THE FCC'S BROADBAND ACCELERATION INITIATIVE (Feb. 9, 2011), available at
http://hraunfoss.fcc.gov/edocs_public/attachmatch/DOC-304571A2.doc.
24 See Julius Genachowski, Chairman, FCC, Remarks at Broadband Acceleration Conference (Feb. 9, 2011),
available at https://www.fcc.gov/Daily_Releases/Daily_Business/2011/db0209/DOC-304571A1.pdf.
25 See FCC to Hold Broadband Acceleration Conference, Public Notice, DA 11-241 (Feb. 8, 2011).
26 The Notice also reflects recent recommendations by the Technological Advisory Committee (TAC), a working
group of industry and technology leaders formed by the Commission last year to consider a variety of issues and
advise the Commission. In particular, on March 30, 2011, the TAC Broadband Infrastructure Deployment Working
Group recommended, among other things, that the Commission: (1) work with other federal agencies to improve
federal rights of way and wireless facilities siting processes; (2) promote best practices and uniformity in rights of
way access and wireless facilities siting requirements, including rate development; (3) highlight the benefits of new
technologies for accelerating broadband deployment; (4) work to reduce the time required for tower siting
applications, especially those involving collocation on existing towers; and (5) encourage localities to develop
means of notifying interested parties of upcoming open trenching projects so that they can install fiber
simultaneously. See generally http://reboot.fcc.gov/video-archives. We note that many of the Working Group
recommendations are discussed in this Notice, and that the Commission may be able to act on such
recommendations independent of this proceeding.
5

Federal Communications Commission

FCC 11-51
is the best way to ensure that all affected parties the relevant governmental entity, citizens and consumer
groups, and other private parties that have sought access in the area are able to respond to specific
examples or criticisms. Identifying with specificity particular examples or concerns will ensure that the
Commission has a complete understanding of the practices and can obtain additional background if
appropriate. In turn, we ask government entities to explain the policy goals underlying their current
practices and charges regarding rights of way and wireless facilities siting. We seek to identify best
practices, systemic challenges and fully consider possible steps the Commission can take, in partnership
with federal, state, local, and Tribal governments--with input from consumer groups and industry--to
foster improvements in these areas.
10.
This Notice explores specific steps that could be taken to identify and reduce unnecessary
obstacles to obtaining access to rights of way and siting wireless facilities. For example, should the
Commission:

Identify and promote best practices and increased uniformity with respect to public rights of
way and wireless facilities siting practices and policies?

Make specific recommendations for action to Congress and the Administration?

Sponsor voluntary mediation of public rights of way or wireless facilities siting disputes
between state or local officials and industry?27

Adopt policy guidelines, adopt rules, or adjudicate rights of way cases, under section 253 or
332 of the Communications Act?
11. Today, the Commission takes the next step in advancing its Broadband Acceleration
Initiative by adopting this Notice and, in a companion item, by reforming pole attachment policies.28
While this Notice covers a broad range of issues, the Commission may move forward in other contexts to
act on individual issues raised here, as appropriate, without awaiting completion of this proceeding.

II.

RIGHTS OF WAY AND WIRELESS FACILITIES SITING ISSUES

12.
In this section, we describe the various types of possible issues regarding rights of way
governance and wireless facilities siting requirements, and we seek input in order to obtain a more
complete understanding of these areas. 29 We seek to develop a complete record of how rights of way and
wireless facilities siting decisions influence build out and adoption of broadband and other
communications services, both to inform Commission decision-making and to inform a broader public
discussion of these issues. We believe that rights of way and wireless facilities siting issues can generally
be broken into several broad categories: (1) timeliness and ease of the permitting process; (2) the
reasonableness of charges; (3) the extent to which ordinances or statutes have been updated to reflect
current communications technologies or innovative deployment practices; (4) consistent or
discriminatory/differential treatment; (5) presence or absence of uniformity due to inconsistent or varying
practices and rates in different jurisdictions or areas; (6) other rights of way concerns including "third
tier" regulation or requirements that cover matters not directly related to rights of way use or wireless
facilities siting. We ask commenters to describe the specific kinds of public rights of way and wireless
facilities siting issues that exist in each of these areas. Do some of these issues particularly affect various


27 We note that some of these ideas were suggested at the Broadband Acceleration Conference the Commission
hosted on February 9, 2011. We incorporate the presentations made during that event in this record and ask
interested parties to consider the perspectives and specific policy ideas raised during that event.
28 See supra note 15.
29 The scope of our request for information on current rights of way governance is not intended to prejudge the
existence of significant problems or the need for any particular remedial approach.
6

Federal Communications Commission

FCC 11-51
categories of rights of way owners, wireless facilities siting authorities, network users, or network
functions?30 We also ask interested parties to describe best practices in each of these areas.

A.

Timeliness and Ease of Permitting Process

13.
The Commission recently addressed the timeliness of state and local permitting processes
for tower siting in the Shot Clock Ruling, which set a timeline for action on collocation and other tower
siting applications.31 We seek comment on the application of the Shot Clock Ruling, and its efficacy in
reducing delays in the local zoning process.32 In particular, has the Shot Clock Ruling reduced the number
of collocations pending before state and local government authorities for periods of longer than 90 days,
and the number of applications other than collocations pending for longer than 150 days? Has this
approached proved satisfactory from the perspective of the communities in resolving actions for
collocation? Have individual cases been taken to district courts for zoning authorities' failure to act, and
if so, how did the courts apply the Shot Clock Ruling? Do parties believe that adoption of the Shot Clock
Ruling
has resulted in faster rulings from state and local government authorities? In answering these
questions, parties should provide as much specificity as possible.
14.
We also seek updated information on the timeliness and ease of permit processing for rights
of way and siting of wireless facilities. Are application processes defined with sufficient clarity? Is
information on all necessary application procedures, forms, substantive requirements, and charges readily
accessible? How do rights of way holders and wireless facilities siting authorities handle new or novel
requests for access to rights of way or tower and antenna sites? Are there processes in place for
addressing situations in which it is difficult to identify the rights of way holder? How could the
application process be streamlined in certain situations, such as where an infrastructure provider seeks to
collocate new facilities on an existing tower? Is the process for obtaining permits for accessing rights of
way or siting wireless facilities timely? To the extent applications are not processed in a timely fashion,
what factors are responsible for delays? Are there types of errors, omissions, or substantive requirements
in applications that frequently lead to rejection, dismissal, or return of the applications? What application
processing timeframes are reasonable? Are there particular practices that can improve processing time
frames?
15.
We also ask commenters to provide data about their experiences and situations. We ask
commenters to submit data related to processing intervals for permit approval, both targeted and actual,
for all relevant providers (data submitted by rights holders) and communities (data submitted by
infrastructure providers). We ask that any submitted data be broken out in as disaggregated a fashion as
possible. For example, we encourage commenters to include for each application the name of the
provider; name of the location (e.g., community name); type of project, including whether a project is
wholly new or an augmentation of an existing facility (e.g., wireless collocation on existing structure);
whether the community is subject to comprehensive state franchising or rights of way laws; and total time
to process applications.33 To the extent that certain activities during a particular approval took an unusual


30 See supra note 5 (describing, for example, different types of entities that own or control rights of way).
31 Petition for Declaratory Ruling To Clarify Provisions of Section 332(c)(7)(B) To Ensure Timely Siting Review
and To Preempt Under Section 253 State and Local Ordinances that Classify All Wireless Siting Proposals as
Requiring a Variance
, WT Docket No. 08-165, Declaratory Ruling, 24 FCC Rcd 13994 (2009) (Shot Clock Ruling);
Order on Reconsideration, 25 FCC Rcd 11157 (2010), appeal pending.
32 See also Letter from Ken Fellman, President, National Association of Telecommunications Officers and Advisors,
to Ruth Milkman, Chief, Wireless Telecommunications Bureau, FCC, WT Docket No. 08-165 (filed May 25, 2010)
(asking that the Commission undertake a proceeding to "analyze the impact" of the Shot Clock Ruling).
33 Insofar as filing parties provide aggregated data, they should seek to ensure that such data involves similar
applications and circumstances, rather than applications involving disparate circumstances.
7

Federal Communications Commission

FCC 11-51
length of time, we encourage participants to provide any relevant details, such as pre-processing time
devoted to obtaining a complete-as-filed application, time spent negotiating, or time spent waiting for
events external to the application process.34 Commenters also should include any other relevant
categories of data or explanations that will make their submissions more informative.

B.

Reasonableness of Charges

16.
To what extent and in what circumstances are rights of way or wireless facilities siting
charges reasonable? Is it possible to identify rights of way or wireless facilities siting charges that all
stakeholders agree are reasonable? If not, are there rate levels that most infrastructure providers agree are
reasonable, and different rate levels that most government entities agree are reasonable? Are there
instances and circumstances in which rights of way or facilities siting charges are unreasonable? What
are appropriate criteria for determining the reasonableness of such charges? For example, are permitting
or application fees unreasonable to the extent they exceed amounts that would recover administrative and
other specifically identifiable costs?35 Are "market based" rates for use of public rights of way or
publicly-owned wireless facilities sites reasonable? In particular, how are market-based rates or other
non-cost based rates for public rights of way determined when, in many situations, there does not appear
to be a competitive market for public rights of way?36 Are market-based rates substantially higher than
cost-based rates?
17.
We ask commenters to provide factual data to help the Commission understand existing
charges and practices. We seek data on current permitting charges, including all recurring and non-
recurring charges, as well as any application, administrative, or processing fees. In presenting these data,
we ask commenters to identify such information as the type of facilities for which such charges are
assessed; how such charges are structured (e.g., per foot or percent of revenue in the case of rights of way
fees); whether the community is subject to comprehensive state franchising or rights of way laws;
whether the charges are published in advance or individually negotiated, designed to approximate market
rates or merely recover costs (direct and/or indirect), and accompanied by comprehensive terms, and
conditions; and the value of any in-kind contributions required for access or permit approval. We also
request commenters to include information that enables us to determine the extent to which such charges
are related to impacts on the local community, such as pavement restoration costs for projects that involve
trenching in roadways. We recognize that certain information may disclose competitively sensitive
information and we understand the need to aggregate such data across multiple communities or providers,
or otherwise present it in a way that does not disclose any competitively sensitive data.
18.
We also seek information on how a market-based charge is calculated in the context of
various types of fees. For example, do per-foot fees and other usage fees vary depending on the number
of providers that need access to the rights of way and the amount of fiber or other facilities each such
provider places in the rights of way (a measure of demand)? To what extent do entities vary such fees
based on other market factors, for example, the available supply, such as the remaining usable space
within a conduit system in the rights of way, or the amount of land available to accommodate a new
system? We also are interested in understanding how the levels of percent-of-revenue fees are set in


34 We also note that processing times can be affected when a large number of applications are filed simultaneously.
35 For example, this could include the cost of street repair necessitated by trenching.
36 For example, in the case of local distribution of wireline communications services to subscribers, there do not
appear to be reasonable alternatives to using local rights of way. Even in the case of long-haul transmission,
alternatives to the use of public rights of way may be significantly less desirable and more expensive. See
Minnesota Order
, 14 FCC Rcd at 21709-12.
8

Federal Communications Commission

FCC 11-51
order to achieve a market-based rate.
19.
We also invite comment on whether there are specific circumstances in which rights of way
or wireless facilities siting charges are more likely to be unreasonable . For example, once an
infrastructure provider has placed facilities in a public right of way, incurring sunk costs, is the public
rights of way holder frequently in a position to exercise market power in establishing subsequent charges,
such as on renewals of long-term contracts or requests to make changes to a vitally important network
facility? Are there specific situations where such market power has been exercised? How can instances
of the exercise of market power be identified? What situations are most likely to cause wireless facilities
siting charges to be unreasonable? Do rights of way or wireless facilities site administrative and/or usage
fees vary by the demographics of the customer base? For example, do holders of public rights of way,
government owners of tower or antenna sites, and/or government entities regulating wireless facilities
sites located in dense, urban, and/or suburban high-income areas tend to impose higher fees than
government entities in other areas, and are such differences reasonable?
20.
We also request comment on the ways in which rights of way or wireless facilities site
processing or usage charges affect broadband subscribers. Are such charges imposed on a broadband
provider ultimately passed on to that provider's customers? What fraction of a broadband provider's
costs do public rights of way and governmental wireless facilities site or administrative fees typically
represent? Insofar as broadband providers charge geographically averaged rates, high rights of way and
wireless facilities siting charges will be recovered by providers in part from consumers in other
jurisdictions rather than recovered directly from consumers within the jurisdiction imposing the high
charges. To what extent should this affect the analysis of rights of way and wireless facilities siting
charges? For example, should we be concerned about excessive charges if they are transparent and
recovered solely from residents of the jurisdiction imposing the charge?

C.

Qualitative Information

21.
We also seek qualitative information that describes how the prices for rights of way and
wireless facilities siting and the target timeframe for approval of infrastructure providers' applications
are set, and that describe the process of receiving approval to access rights of way or site wireless
facilities, particularly for broadband. How are we to distinguish and evaluate different policies and
practices? To help create a record of existing and best practices, we ask infrastructure providers,
localities, and other interested parties to submit examples of model, typical, and problematic franchising
or access agreements.
22.
Certain qualitative information we seek is best provided by states and localities. For
instance, we request information on the policy goals and other objectives underlying practices and
charges related to access to rights of way and approval of wireless facilities. To what extent are local
requirements designed to achieve public interest goals, such as ensuring public safety, avoiding
disruption of traffic, or maintaining roadways? What role do other civic goals play in guiding local
rights of way and wireless governance decisions? For example, how do localities weigh such issues as
preventing the public disruption and damage to roads that accompanies street cuts, or satisfying
aesthetic, environmental, or historic preservation concerns, with goals of greater fixed and mobile
broadband deployment and adoption through timely processing of permits, nondiscrimination,
transparency, and reasonable charges?
23.
Certain other information we seek may be best provided by infrastructure providers. For
example, we seek information about how rights of way issues influence the deployment decisions of
infrastructure providers. In this regard, we request information on both specific instances in which a
provider chose not to build out broadband facilities due to rights of way concerns and comprehensive data
or analysis that might demonstrate the extent to which rights of way concerns are impeding broadband
infrastructure investment and broadband adoption. As providers prioritize capital investments, to what
extent do rights of way and wireless siting governance issues have an effect? How do providers take into
9

Federal Communications Commission

FCC 11-51
account any uncertainty with regard to cost or timing? In areas where processes have been standardized,
we ask providers to provide evidence of how this has affected their deployment decisions and quantify
any benefits. Are there situations in which localities believe that infrastructure providers have
unreasonably refused to build out broadband facilities despite best efforts on the part of the locality to
encourage deployment through rights of way or wireless facility siting policies?

D.

Extent To Which Ordinances or Statutes Have Been Updated To Reflect Current
Communications Technologies or Innovative Deployment Practices

24.
We ask interested parties whether state statutes or local ordinances have been updated to
reflect current developments in the communications industry or recent changes in communications
technologies that require access to public rights of way. Where such updates have not occurred, do
providers experience problems or issues with application processing or delays? For example, do existing
ordinances or other requirements successfully address the placement of small antennas on existing
facilities in rights of way? In particular, we seek comment on any challenges that may apply to the
deployment of microcells, picocells, femtocells, and Distributed Antenna Systems (DAS).37 What, if
anything, do states and localities require in order to permit the attachment of microcells, picocells,
femtocells, and DAS antennas to existing infrastructure that is different from attaching any other antenna
to a given structure? Do any states or localities allow all of the proposed DAS antennas within a DAS
network to be combined in a single permit application, and is this or would this be helpful for DAS
deployment? Are there any other ways in which microcells, picocells, femtocells, and DAS antennas are
treated uniquely, and are there any ways in which states, localities, or wireless service providers think
they should be treated differently? To what extent are these facilities treated as public utilities? To what
extent are they subject to local zoning processes? To what extent should existing ordinances or statutes
be revised to reflect changes in the communications industry and technology?
25.
We also seek comment on how different jurisdictions treat the use of existing infrastructure
for wireless services, both in and out of rights of way. Is there disparate treatment between a pole
attachment, i.e., the attachment of a wireless antenna to an existing public utility pole, and a collocation,
where a wireless antenna is attached to some other existing structure? Are different or additional
considerations required for some types of rights of way, such as those used for transportation, as
compared to other types? Are there instances in which conflicting laws may apply to the attachment of a
wireless antenna to an existing structure? What is the overall effect of these considerations on the ability
and the likelihood that existing infrastructure can be effectively used to deploy wireless services? Do
some regulations and policies encourage resource sharing, while others discourage it? Do states and
localities show any preference for collocated antennas or for the placement of wireless facilities on public
property? Are there particular approaches that facilitate wireless deployment, including DAS? Why do
they work well?


37 Microcells, picocells, and femtocells are relatively small, low-cost wireless base stations that typically cover a
smaller area than ordinary macrocells and increase coverage and capacity of wireless networks. By allowing
providers to increase the density of their network cost-effectively, these kinds of technologies enable more efficient
"spatial reuse" of the nation's scarce spectrum resource. Similarly, a DAS is a network of antennas that provide
wireless service within a given geographic area or structure. DAS antennas are generally smaller, lower-powered
antennas that are located below the clutter level of nearby trees or buildings. DAS can be especially useful to fill
holes in wireless coverage areas, such as inside buildings, in urban areas, and in places where topography interferes
with the delivery of a wireless signal from a single, higher-powered, taller facility. See generally DAS Forum
Comments at 12-13 and Next G Comments at 21, Implementation of Section 224 of the Act and A National
Broadband Plan
, WC Docket No. 07-245 and GN Docket No. 09-51; Letter from William J. Sill, Counsel, ATC
Outdoor DAS, LLC, to Marlene H. Dortch, Secretary FCC, WC Docket No. 07-245 (filed Mar. 15, 2011).
10

Federal Communications Commission

FCC 11-51

E.

Consistent or Discriminatory/Differential Treatment

26.
How have ordinances addressed differences in rights of way users and wireless facilities
siting applicants, the different uses they make of rights of way and sites, and the different equipment they
seek to deploy? Are differing rights of way or wireless facilities siting practices or charges reasonable?
Do they involve unreasonable or discriminatory differential treatment of various types of rights of way
users or facilities siting applicants? What are appropriate methods to determine whether a practice or
charge is unreasonable or discriminatory? For example, do publicly available fee schedules for various
categories of rights of way use tend to be nondiscriminatory? Are zoning requirements for wireless
facilities siting nondiscriminatory? Are there other criteria that can and should be used to determine
whether charges or practices are discriminatory without fact-intensive and burdensome administrative or
court proceedings?

F.

Presence or Absence of Uniformity Due to Inconsistent or Varying Practices and
Rates in Different Jurisdictions or Areas

27.
In a given metropolitan area, the main city and various surrounding towns, villages, and
counties may have differing practices and charges for rights of way usage and wireless facilities siting.
To what extent do these practices and charges differ within a particular state? Does inconsistent treatment
of infrastructure providers among states and localities make the deployment of broadband more difficult
or time-consuming, or is inconsistency among states and/or localities not problematic as long as
infrastructure providers have a clear path to follow within each jurisdiction? To what extent does the
need to file multiple applications cause problems for infrastructure providers, regardless of the similarity
or differences in the practices and charges involved?
28.
To what extent do rights of way governance and wireless facilities siting requirements vary
between different federal government agencies? Do different agencies require varying types of
information or do different agencies require similar information to be presented in different formats? To
what extent do any differences among agencies make it more difficult to obtain permits and build out
broadband networks on federally controlled properties? Have there been efforts to increase uniformity?
How successful have they been?

G.

Other Issues

29.
Other Rights of Way or Wireless Facilities Siting Issues: We ask interested persons to
identify and describe any other rights of way or wireless facilities siting issues that have an impact on
broadband deployment and adoption. We also ask interested parties to identify any other practices or
approaches that have been particularly beneficial to facilitating broadband deployment. Do government
rights of way owners or wireless facilities siting authorities impose requirements that are not directly
relevant to intended use? For example, in some cases in the past, localities owning rights of way have
required that infrastructure providers supply information of the type usually required for a certificate of
operating authority from the state.38 Is this an ongoing requirement for applicants seeking rights of way
or siting permits? Are there other examples of such requirements? What are the policy reasons for
such requirements? Are there adjustments that could be made to ensure that localities obtain necessary
information and addressing legitimate concerns?
30.
Private Rights of Way and Tower Sites: We ask interested persons to provide information
on issues that arise in the context of private rights of way or tower sites to the extent such information
might be helpful to the Commission in achieving a complete understanding of potential public rights of
way issues or issues concerning tower siting on public lands.
31.
General Scope of Concerns: We seek comment on whether specific rights of way and


38 See, e.g., TCI Cablevision of Oakland County, Inc., 12 FCC Rcd 21396, 21441 (1997).
11

Federal Communications Commission

FCC 11-51
wireless facilities siting concerns are widespread or generally limited to particular federal agencies, states,
Tribes, and localities. Are rights of way and wireless facilities siting concerns generally less widespread
in states that have adopted comprehensive rights of way laws than in other states? Are rights of way and
wireless facilities siting concerns more common in certain types of areas, such as cities and surrounding
suburbs, and less common in rural areas? We also ask interested persons to comment on the extent to
which rights of way and wireless facilities siting concerns are likely to increase or decrease in the near
future. For example in other contexts, it appears that many long-term rights of way contracts will expire
in the next few years. Is this likely to cause a spike in rights of way disputes? Will the need for new
facilities to provide next generation wireless services increase concerns regarding facilities siting?
32.
Additional Data Gathering: We seek input on whether the Commission should take any
additional steps to gather information on issues relevant to this proceeding, including workshops, surveys,
and/or mandatory data collections. Are there any existing sources of relevant data the Commission could
rely on for purposes of this proceeding?
33.
We seek input on the costs and benefits of each of these approaches and whether any of
these approaches should be pursued in this proceeding. Are there any other approaches that would yield
better results with similar or smaller investments of time and effort?

III.

SOLUTIONS

A.

Prior Efforts To Resolve Concerns

34.
We seek information on what interested parties have already done to address rights of way
and wireless facilities siting concerns.
35.
Have the federal government, states, localities, Tribes, and/or the organizations
representing them developed best practices for rights of way and wireless facilities siting governance?
We also seek comment on best practices proposed by private sector entities. Are there existing
compendia of rights of way and wireless facilities siting best practices? Aside from state statutes, have
there been efforts to develop consolidated rights of way application processes that cover multiple
jurisdictions and reduce or eliminate the need to file multiple applications? Have other approaches to
improving rights of way and wireless facilities siting governance been attempted? We request comment
on the effects of previous efforts to address rights of way and wireless facilities siting governance. Have
state statutes governing rights of way helped increase uniformity and reduce costs? We encourage states
that have adopted such legislation to describe the approach adopted as well as the benefits and
drawbacks.39 In addition, we ask interested persons to submit information on instances in which
government entities and industry have worked together in a positive manner to foster broadband
deployment, and describe the factors or circumstances that led to such constructive collaboration.

B.

Options Possible Actions To Address Current Areas of Concern

36.
In this section, we ask interested persons to comment on a number of actions the
Commission might take to foster broadband deployment by addressing rights of way and wireless
facilities siting concerns. For analytical purposes we have broken the options into two groups: One
focused primarily on possible voluntary programs and educational activities coordinated or facilitated by
the Commission, and the other involving the exercise of Commission rulemaking or adjudicatory
authority. These sets of options are not mutually exclusive. We ask interested parties to comment on the
benefits and costs of each of these potential actions, and to quantify those benefits and costs to the extent
possible. We also ask interested parties to comment on the extent of the Commission's authority to take
the various actions discussed below, particularly the Commission's authority to engage in rulemaking


39 NTIA gathered extensive information on state rights of way statutes in 2003 and posted it online. See NTIA,
RIGHTS OF WAY LAWS BY STATE, available at http://www.ntia.doc.gov/ntiahome/staterow/rowtableexcel.htm.
12

Federal Communications Commission

FCC 11-51
and/or adjudication. We also ask whether there are other effective options to foster broadband
deployment through improvements in rights of way or wireless facilities siting governance.
1.

Voluntary Programs and Educational Activities

37.
Commission Educational Efforts and Voluntary Activities: Should the Commission
address rights of way and wireless facilities siting concerns through educational efforts and voluntary
activities? We ask interested parties to focus on the substantive scope of such educational voluntary
activities described below.
38.
Best/Worst Practices: Should the Commission compile a set of best practices for public
rights of way and wireless facilities siting policies that are consistent with facilitating broadband
deployment? If so, how should this be done? Should this effort focus on a limited set of problematic
issues, or should we instead try to develop a comprehensive set of best practices?
39.
Increased Uniformity: Closely related to the issue of best practices, although emphasized
somewhat differently, is the issue of increased uniformity. Should the Commission work to increase
uniformity in rights of way and wireless facilities siting governance among localities and/or within the
federal government? Could the Commission, in partnership with affected stakeholders, develop a model
application processes or other procedures or practices, to lower costs and streamline processes across
multiple jurisdictions?
40.
With respect to uniformity in practices and procedures within the federal government, what
if any steps should the Commission take to help streamline the process of siting facilities on federal
lands?40 Should the Commission, for example, recommend convening or participating in an inter-agency
task force to inventory current procedures and identify benchmarks for best practices?
41.
Competitions and Awards: We also ask interested parties to comment on whether the
Commission should encourage best practices and increased uniformity by initiating a "race to the top"
type of competition. The Commission could promote streamlined processes that provide timely access to
rights of way and wireless facilities siting by recognizing individual localities for their outstanding efforts
on these issues. By doing so, the Commission would be encouraging more localities and states to
implement rights of way or wireless facilities siting best practices and/or increase uniformity in these
areas. What kinds of incentives would encourage participation by localities and states?41
42.
Commission Sponsored Mediation: Should the Commission establish a process for
voluntary mediation of rights of way and wireless facilities siting disputes by selected state or local
representatives working in conjunction with industry? 42 How should such a process be structured, and
how could participation be encouraged?
43.
Improved Facilities Deployment Practices in Rights of Way: Should the Commission work
to raise awareness about facilities deployment techniques that could reduce costs and speed deployment?
For example, should the Commission promote micro trenching and deployment of Distributed Antenna


40 We note that the Commission is currently seeking comment in another proceeding on the effectiveness of the
Tower Construction Notification System (TCNS) and the processes we should follow in deciding whether to grant
requests for access to the TCNS to other federal agencies. See Improving Communications Services for Native
Nations
, CG Docket No. 11-41,Notice of Inquiry, FCC 11-30, (Mar. 4, 2011).
41 See generally America COMPETES Act, Pub. L. 110-69 1102(a)(11), 1006(b)(1)-(2), 1006(d)(1)., 121 Stat.
571, 575-79 (2007); America COMPETES Reauthorization Act of 2010, Pub. L. No. 111-358 803, 124 Stat. 3981,
4005 (2011).
42 Memorandum to Sharon Gillett, Chief, Wireline Competition Bureau, FCC from Ken Fellman, President NATOA
(Feb. 22, 2011).
13

Federal Communications Commission

FCC 11-51
System facilities on street light and traffic light poles where appropriate? We invite comment on other
innovative rights of way or wireless facilities deployment practices that should be considered in this
regard.
44.
Recommendations to Congress or the Administration: The National Broadband Plan
recommended that "Congress should consider allowing all agencies to set the fees for access to rights of
way for broadband services on the basis of a direct cost recovery approach, especially in markets
currently underserved or unserved by any broadband service provider."43 The Plan also recommended
that the Executive Branch "develop one or more master contracts for all federal property and buildings
covering the placement of wireless towers."44 Are there additional specific actions that the Commission
should recommend to the Administration or to Congress that would remove roadblocks and encourage
further broadband build out on federal properties? For example, should the Commission recommend that
the Executive Branch formally permit wireless facility sites on federal property, including postal service
property? Should the Commission make recommendations to Congress or the Administration concerning
rights of way or wireless facilities siting concerns? For example, is legislation needed to address certain
concerns? Would Congressional action promote uniformity? Should the Commission make
recommendations to the Administration? We invite suggestions for specific legislative language
recommended for Congress.
2.

Rulemaking and Adjudication

45.
In this section we discuss possible rulemaking and adjudication options. We note that these
options may work well as backstops to voluntary action and Commission educational efforts or in
combination with such options.
46.
Adopt Policy Guidelines: Should the Commission adopt policy guidelines addressing
rights of way or wireless facilities siting issues? Such guidelines could set out the Commission's views
on various issues, such as application processing time frames, but would not be enforceable as rules. We
invite comment on the policy benefits and drawbacks of this option.
47.
Adopt Rules: Should the Commission adopt rules designed to foster broadband
deployment by addressing rights of way or wireless facilities siting problems?
48.
Substantive Scope of Policy Guidelines or Rules: What subjects should be addressed by
any policy guidelines or rules adopted by the Commission? For example, should the Commission address
the issues described below? Are there other substantive issues in this proceeding that the Commission
should address through policy guidelines or rules?

Safe Harbors/Triggers: Should the Commission adopt policy guidelines or rules
establishing safe harbors for rights of way and wireless facilities siting procedures,
practices, and charges; or triggers that would subject such procedures, practices, and
charges to heightened scrutiny by the Commission or a court in particular circumstances?
If so, what procedures, practices, and rates should be included in this approach?

Billing Practices: Should the Commission adopt guidelines or rules allowing or requiring
infrastructure providers to impose separate line item fees to recover rights of way or
wireless facilities siting charges directly from subscribers in the jurisdiction imposing such
charges in order to increase transparency and accountability and minimize cross-subsidies?


43 NATIONAL BROADBAND PLAN at 133.
44 Id.
14

Federal Communications Commission

FCC 11-51

Interpretation of Sections 253 and 332:45 Should the Commission adopt guidelines or rules
interpreting the terms of these statutory provisions with respect to rights of way and
wireless facilities siting requirements? If so, what provisions of each section should the
Commission address and how should those provisions be interpreted?
49.
Adjudication: Should the Commission address certain rights of way problems through
adjudication under section 253? Would this approach be well suited to addressing problems that are not
widespread, but may represent significant obstacles to broadband deployment in a particular locality or a
small number of localities?
3.

Other Proposals

50.
We also invite interested parties to suggest other specific actions the Commission could
take to improve policies regarding public rights of way and wireless facilities siting. In each case, we ask
them to describe the problem or subject matter addressed and its effect on broadband deployment. We
then ask them to explain their proposal. We also ask interested persons to describe the benefits of such
proposals and to address potential drawbacks. In addition, we ask interested persons to identify proposals
that can be implemented relatively quickly and those that would take longer to implement, along with
suggested timelines.

IV.

LEGAL AUTHORITY

51.
We believe the Commission has authority to engage in educational activities to foster
broadband deployment through improved policies regarding public rights of way and wireless facilities
siting and to coordinate and participate in voluntary activities designed to achieve this goal. We also
believe the Commission has authority to adopt policy guidelines and rules concerning these issues. We
ask for comment on these views and on whether the Commission has authority to adjudicate rights of way
cases under section 253. An analysis of these legal issues is set forth below. In this regard, we emphasize
that the views described here do not represent final determinations on these issues and that our ultimate
legal conclusions will reflect a careful consideration of the comments addressing these issues.

A.

Background

52.
We begin by reviewing the terms of the statutory provisions most relevant to this
proceeding section 706 of the 1996 Telecommunications Act and sections 253 and 332(c)(7) of the
Communications Act. We also address a number of additional statutory provisions in this section.
53.
Section 706(a) provides that the Commission "shall encourage the deployment on a
reasonable and timely basis of advanced telecommunications capability to all Americans (including, in
particular, elementary and secondary schools and classrooms). . . ."46 In granting the Commission
authority to fulfill this mandate, Congress specifically directed the Commission to use various regulatory


45 As noted above, the Commission has previously interpreted several provisions in Section 332(c)(7). In the Shot
Clock Ruling
, to ensure a timely review of siting applications and to prevent unnecessary delay, the Commission
interpreted a "reasonable period of time" under section 332(c)(7) of the Communications Act as 90 days for
collocations and 150 days for all other applications. The Commission also found that it is a violation of section
332(c)(7)(B)(i)(II) of the Communications Act for a state or local government to deny a personal wireless service
facility siting application because service is available from another provider. See Shot Clock Ruling, 24 FCC Rcd
13994 (2009).
46 47 U.S.C. 1302(a); see also S. Rep. No. 104-23, at 51 (1995) ("The goal is to accelerate deployment of an
advanced capability that will enable subscribers in all parts of the United States to send and receive information in
all its forms--voice, data, graphics, and video--over a high-speed switched, interactive, broadband, transmission
capability.").
15

Federal Communications Commission

FCC 11-51
methods, including those that "remove barriers to infrastructure investment."47 In the 2010 Sixth
Broadband Deployment Report
, the Commission concluded that broadband was not being deployed to all
Americans in a reasonable and timely manner.48 When the Commission makes such a negative
determination, section 706(b) requires that the agency "take immediate action to accelerate deployment of
[broadband] by removing barriers to infrastructure investment and by promoting competition in the
telecommunications market."49
54.
Section 253(a) bars state or local statutes, regulations, or other legal requirements that
"prohibit or have the effect of prohibiting the ability of any entity to provide any interstate or intrastate
telecommunications service."50 Section 253(b) contains a safe harbor preserving state action imposing
"on a competitively neutral basis . . . requirements necessary to preserve and advance universal service,
protect the public safety and welfare, ensure the continued quality of telecommunications services, and
safeguard the rights of consumers."51 Section 253(c) also preserves the "authority of a State or local
government to manage the public rights-of-way or to require fair and reasonable compensation from
telecommunications providers, on a competitively neutral and nondiscriminatory basis . . . ."52 Section
253(d) expressly requires the Commission to preempt state or local government action in certain
situations.53
55.
Section 332(c)(7) of the Act applies to rights of way issues concerning wireless services,
Section 332(c)(7) preserves state and local authority over decisions regarding the placement, construction,
and modification of personal wireless service facilities subject to certain limitations."54 Among other
limitations, section 332(c)(7) states that "[t]he regulation of the placement, construction, and modification
of personal wireless service facilities by any State or local government or instrumentality thereof . . . shall
not prohibit or have the effect of prohibiting the provision of personal wireless services."55 It also
requires the State or local government to act on any request to place, construct, or modify personal
wireless service facilities "within a reasonable period of time . . . taking into account the nature and scope
of such request."56 It permits a person adversely affected by any final action or failure to act by the State
or local government to commence an action in court within 30 days after such final action or failure to


47 47 U.S.C. 1302(a).
48 See Inquiry Concerning the Deployment of Advanced Telecommunications Capability to All Americans in a
Reasonable and Timely Fashion, and Possible Steps to Accelerate Such Deployment Pursuant to Section 706 of the
Telecommunications Act of 1996, as Amended by the Broadband Data Improvement Act
, GN Docket Nos. 09-137,
Sixth Broadband Deployment Report, 25 FCC Rcd 9556, 9557, para. 1 (2010) (2010 Sixth Broadband Deployment
Report
) (estimating that 14-24 million Americans still lacked access to broadband).
49 47 U.S.C. 1302(b); see also S. Rep. No. 104-23, at 50 (1995) ("If the FCC makes a negative determination, it is
required to take immediate action to accelerate deployment.").
50 47 U.S.C. 253(a).
51 47 U.S.C. 253(b).
52 47 U.S.C. 253(c).
53 47 U.S.C. 253(d).
54 47 U.S.C. 332(c)(7)(A). Personal wireless service facilities are defined in section 332(c)(7)(C)(ii) as "facilities
for the provision of personal wireless services" and personal wireless services are defined in section 332(c)(7)(C)(i)
as "commercial mobile services, unlicensed wireless services, and common carrier wireless exchange access
services." 47 U.S.C. 332(c)(7)(C)(i)-(ii).
55 47 U.S.C. 332(c)(7)(B)(i)(II).
56 47 U.S.C. 332(c)(7)(B)(ii).
16

Federal Communications Commission

FCC 11-51
act.57

B

Authority for Educational Activities and Voluntary Programs

56.
We believe the Commission has ample authority to engage in educational efforts to foster
broadband deployment by encouraging improvements in policies regarding public rights of way and
wireless facilities siting. We also think the Commission has ample authority to participate in or facilitate
voluntary endeavors to achieve this goal. Section 706(a) specifically charges the Commission with
encouraging the deployment of broadband through the use of methods that remove barriers to
infrastructure investment. Section 1 of the Act also states that the Commission was created to ensure
rapid, efficient communication services. In addition, section 4(i) gives the Commission broad authority to
take whatever actions are necessary to the execution of its functions as long as they are not otherwise
inconsistent with the Act. Education and involvement in voluntary programs would advance the goals of
section 706 and section 1 and come within the broad flexibility accorded the Commission under section
4(i). We believe that such activities also further the goals of sections 253 and 332 by reducing the
likelihood of state or local actions that have the effect of prohibiting the provision of a
telecommunications service or personal wireless service in violation of those sections. We seek comment
on these issues.

C.

Authority for Rulemaking

57.
We also believe that the Commission has authority to engage in rulemaking to improve
rights of way and wireless facilities siting governance. Section 201(b) states that the "Commission may
prescribe such rules and regulations as may be necessary in the public interest to carry out the provisions
of this Act."58 Section 303(r) contains a similar grant of rulemaking authority59 and section 4(i)
authorizes the Commission to, among other things, "make such rules and regulations, and issue such
orders . . . as may be necessary in the execution of its functions."60 Thus, we believe the Commission has
broad general rulemaking authority that would allow it to issue rules interpreting sections 253 and 332.
We seek comment on this view. Could the Commission, for example, adopt rules further defining when a
state or local legal requirement constitutes an effective barrier to the provision of a telecommunications
service under section 253(a)61 or defining what constitutes fair and reasonable compensation under
section 253(c)? We also seek comment on our authority to adopt rules concerning matters in this
proceeding pursuant to section 706.

D.

Adjudication of Rights of Way Cases Under Section 253

58.
We also invite comment on whether the Commission has authority to adjudicate rights of
way disputes under section 253. Some parties have argued that the Commission does not have such


57 47 U.S.C. 332(c)(7)(B)(v). In the case of an action or failure to act that is impermissibly based on the
environmental effects of radio frequency emissions pursuant to section 332(c)(7)(B)(iv), a person adversely affected
may also petition the Commission for relief. Id.
58 47 U.S.C. 201(b). Commission authority to adopt rules pursuant to section 201(b) in the absence of a specific
delegation of such authority has been upheld in the context of cable regulation. See Alliance for Community Media,
529 F.3d 763, 772-76 (6th Cir. 2008), cert. denied, 129 S. Ct. 2821 (2009).
59 47 U.S.C. 303(r). Section 303(r) states in relevant part, "[e]xcept as otherwise provided in this Act, the
Commission from time to time, as public convenience, interest, or necessity requires shall-- . . . make such rules and
regulations and prescribe such restrictions and conditions, not inconsistent with law, as may be necessary to carry
out the provisions of this Act." Id.
60 47 U.S.C. 154(i).
61 See California Payphone Association Petition for Preemption of Ordinance No. 576 NS of the City of Huntington
Park California Pursuant to Section 253(d) of the Communications Act of 1934
, 12 FCC Rcd 14191 (1997).
17

Federal Communications Commission

FCC 11-51
authority.62 These arguments stem in large part from the language and legislative history of section
253(d). Section 253(d) requires the Commission to preempt if it finds a violation of section 253(a)
(barring certain state or local requirements) or (b) (providing a safe harbor for specified state
requirements), but does not address section 253(c) involving rights of way.63 Other parties argue that the
Commission has authority to adjudicate rights of way cases and preempt under section 253.64 The
Commission has not taken action to resolve this issue65 and courts have taken differing approaches.66
Moreover, to the extent that the statutory language is ambiguous,67 the Commission is not bound by those
courts' statutory interpretations.68

V.

PROCEDURAL MATTERS

Paperwork Reduction Act

59.
This document does not contain proposed information collection(s) subject to the
Paperwork Reduction Act of 1995 (PRA), Public Law 104-13. In addition, therefore, it does not contain
any new or modified information collection burden for small business concerns with fewer than 25
employees, pursuant to the Small Business Paperwork Relief Act of 2002, Public Law 107-198, see 44
U.S.C. 3506(c)(4).

Ex Parte Presentations

60.
This proceeding shall be treated as a "permit-but-disclose" proceeding in accordance with
the Commission's ex parte rules.69 Persons making oral ex parte presentations are reminded that
memoranda summarizing the presentations must contain summaries of the substance of the presentations
and not merely a listing of the subjects discussed. It is generally required to have more than a one or two


62 See, e.g., supra note 10, Opposition of New York State Thruway Authority at 14-19.
63 Section 253(d) originally required preemption in the case of violations of sections 253(a), (b) or (c), but the
reference to section 253(c) was removed as the result of an amendment sponsored by Senator Gorton.
64 See, e.g., Level 3 Petition for Declaratory Ruling, Level 3 Petition for Declaratory Ruling that Certain Right-of-
Way Rents Imposed by the New York State Thruway Authority Are Preempted Under Section 253
, WC Docket No.
09-153 at 28-30 (filed July 23, 2009).
65 See Minnesota Order at 21730. In the Minnesota Order, to address Minnesota's request for a declaratory ruling
that its proposed actions were consistent with Section 253, the Commission considered the safe harbor provisions of
section 253(c), finding that Minnesota's proposal did not come within the scope of that provision. However, the
Commission cautioned that "[o]ur discussion of these issues should not be interpreted as addressing potential issues
involving the Commission's jurisdiction under Section 253(c)." Although a number of parties asked the
Commission to preempt Minnesota's proposed action, the Commission declined to act on those requests. Id.
66 See, e.g., BellSouth Telecomm. Inc. v. Town of Palm Beach, 252 F.3d 1169, 1189 (11th Cir. 2001) (discussing
cases).
67 See id. at 1187 ("[A]n analysis of the statutory language creates more questions than it answers about what causes
of action Congress intended to create and who it intended to enforce them."). See also, New Jersey Payphone Assn,
Inc. v. Town of West New York
, 299 F.3d 235, 240 (3rd Cir. 2002) ("Section 253 is quite inartfully drafted and has
created a fair amount of confusion.").
68 National Cable & Telecommunications Association v. Brand X Internet Services, 545 U.S. 967 (2005).
69 47 C.F.R. 1.1200 et seq. Although a Notice of Inquiry proceeding is generally exempt from the ex parte rules,
we find that the public interest is best served by treating this important matter as a "permit-but-disclose" proceeding.
See 47 C.F.R. 1.1200(a), 1.1204(b)(1).
18

Federal Communications Commission

FCC 11-51
sentence description of the presented views and arguments.70 Other requirements pertaining to oral and
written presentations are set forth in section 1.1206(b) of the Commission's rules.71

Comment Filing Procedures

61.
Pursuant to sections 1.415, 1.419, and 1.430 of the Commission's rules,72 interested
persons may file comments and replies regarding the Notice on or before the dates indicated on the first
page of this document.

All filings related to this Notice should refer to WC Docket No. 11-59

.
Comments may be filed using: (1) the Commission's Electronic Comment Filing System (ECFS), (2) the
Federal Government's eRulemaking Portal, or (3) by filing paper copies. See Electronic Filing of
Documents in Rulemaking Proceedings
, 63 FR 24121 (1998).
Electronic Filers: Comments may be filed electronically using the Internet by accessing
the ECFS: http://fjallfoss.fcc.gov/ecfs2/ or the Federal eRulemaking Portal:
http://www.regulations.gov. Filers should follow the instructions provided on the website
for submitting comments.
Paper Filers: Persons who choose to file by paper must file an original and four copies of
each filing.
Filings can be sent by hand or messenger delivery, by commercial overnight courier, or by
first-class or overnight U.S. Postal Service mail. All filings must be addressed to the
Commission's Secretary, Office of the Secretary, Federal Communications Commission.
All hand-delivered or messenger-delivered paper filings for the Commission's Secretary
must be delivered to FCC Headquarters at 445 12th St., SW, Room TW-A325,
Washington, DC 20554. The filing hours are 8:00 a.m. to 7:00 p.m. All hand deliveries
must be held together with rubber bands or fasteners. Any envelopes must be disposed of
before entering the building.
Commercial overnight mail (other than U.S. Postal Service Express Mail and Priority
Mail) must be sent to 9300 East Hampton Drive, Capitol Heights, MD 20743.
U.S. Postal Service first-class, Express, and Priority mail must be addressed to 445 12th
Street, SW, Washington DC 20554.

Accessible Formats

62.
To request materials in accessible formats for people with disabilities (Braille, large print,
electronic files, audio format), send an e-mail to fcc504@fcc.gov or call the Consumer and Governmental
Affairs Bureau at 202-418-0530 (voice) or 202-418-0432 (TTY). Contact the FCC to request reasonable
accommodations for filing comments (accessible format documents, sign language interpreters, CART,
etc.) by e-mail: FCC504@fcc.gov; phone: 202-418-0530 or TTY: 202-418-0432.


70 See 47 C.F.R. 1.1206(b)(2).
71 47 C.F.R. 1.1206(b).
72 47 C.F.R. 1.415, 1.419, 1.430.
19

Federal Communications Commission

FCC 11-51

VI.

ORDERING CLAUSES

63.
Accordingly, IT IS ORDERED that, pursuant to sections 4(i), 4(j), 253, and 332 of the
Communications Act of 1934, as amended, 47 U.S.C. 154(i), 154(j), 253, 332, and section 706 of the
Telecommunications Act of 1996, as amended, 47 U.S.C. 1302, this Notice of Inquiry IS ADOPTED.
64.
IT IS FURTHER ORDERED that interested parties may file comments no later than 60
days after publication and replies no more than 105 days after publication in the Federal Register.
FEDERAL COMMUNICATIONS COMMISSION
Marlene H. Dortch
Secretary
20

Federal Communications Commission

FCC 11-51

STATEMENT OF

CHAIRMAN JULIUS GENACHOWSKI

Re:
Implementation of Section 224 of the Act, WC Docket No. 07-245, A National Broadband
Plan for Our Future
, GN Docket No. 09-51
Re:
Acceleration of Broadband Deployment: Expanding the Reach and Reducing the Cost of
Broadband Deployment by Improving the Policies Regarding Public Rights of Way and
Wireless Facilities Siting,
WC Docket No. 11- 59
Today, we take a major step in reducing barriers to broadband deployment, even as we
set the stage for further progress on this vital goal. Our actions will enable and accelerate billions
of dollars of private investment in the 21st century infrastructure America needs to create jobs,
grow our economy, and compete globally.
Today's actions implement key recommendations of the National Broadband Plan and
are central pillars of our Broadband Acceleration Initiative, announced on February 9. This
Initiative is one of the Commission's top priorities: an agency-wide effort to speed the build-out
of wired and wireless broadband by removing obstacles to deployment, particularly obstacles
created by unneeded or inefficient regulation.
Having determined that broadband is not being reasonably and timely deployed to all
Americans, the Commission is required by Section 706 of the Telecommunications Act to "take
immediate action to accelerate deployment . . . by removing barriers to infrastructure
investment." The Broadband Acceleration Initiative, and our actions today, are central to carrying
out that duty.
The Initiative incorporates work being done by the Commission's Technological
Advisory Council. I was pleased to revive the TAC, announce its new members on October 21,
and give them a concrete charge: identify ways to use communications technologies and
spectrum to drive job creation and economic growth. Under the excellent leadership of Tom
Wheeler, and with participation from a host of private sector experts and Internet pioneers, the
TAC has already identified several promising policy proposals that I look forward to the
Commission considering in the coming year.
Another key milestone was the Broadband Acceleration Conference we held earlier this
year, which yielded a number of strong ideas for policy reforms, many of which are included in
the Notice of Inquiry the Commission adopts today.
Why is this Initiative so important? In the race for global competitiveness, the speed with
which we can build America's broadband networks is as important as the speed that is delivered
over these networks. Broadband is indispensable infrastructure for improving America's
productivity in the 21st century which is in turn the key to robust economic growth and job
creation. The faster we can build out broadband, the faster we can help American workers and
small businesses create the leading web-based enterprises of tomorrow. That's what the
Broadband Acceleration Initiative is all about.
The Pole Attachments Order we adopt today comprehensively reforms the Commission's
pole attachment rules for the first time since the 1990s, taking account of major changes in the
marketplace and incorporating smart policies pioneered by various states.
21

Federal Communications Commission

FCC 11-51
Some might wonder what the connection is between utility poles and broadband service.
Utility poles are essential to providing broadband service, wired and wireless, because that's
where communications companies string cables and, increasingly, place wireless antennas. If
every company that wanted to provide broadband service had to build its own separate set of
poles to carry its equipment, we wouldn't have much broadband in this country--it would simply
be too expensive, and often impossible, to build an entirely new network of poles. This is why the
Commission has historically taken steps to ensure that communications providers have reasonable
access to the poles that already exist throughout the country.
The record in this proceeding demonstrates that today, the process by which broadband
providers get access to utility poles frequently is so unpredictable, takes so long, and costs so
much that it discourages providers from entering the marketplace and significantly delays
broadband build-out. So our Order provides for a fixed timeline for getting access to poles that
providers can count on, for both wired and wireless broadband build-out.
It also provides a timeline for accessing the tops of poles, which are key for the
deployment of wireless broadband technologies like distributed antenna systems DAS for short.
DAS deployments use multiple antennas to extend wireless coverage and provide service more
efficiently than conventional wireless antennas. As a result of this Order, DAS providers estimate
that their cumulative capital investment could total more than $15 billion over the next six years.
Importantly, the Order balances the need for efficient access to poles with protections for
the safety and reliability of our electric grid, and empowers utilities to effectively prevent
unauthorized attachments on their poles. Lineworkers perform jobs that are both valuable and
dangerous, and we have been careful in developing this Order to make sure that we do nothing
that would jeopardize their safety or the safety of others.
The Order also reforms policies for pole attachment rates. The record shows that pole
rental rates vary widely and are often inefficiently high, which slants the competitive playing
field, distorts infrastructure investment decisions, and deters broadband build-out. This is why
incumbent phone companies argued that the Commission should regulate the prices they pay to
access a utility's network of poles.
Reforming pole attachment rates is particularly important for rural America, where this
Order will reduce pole rental costs for some broadband providers by more than 50%. This should
spur broadband deployment where it is needed most, reduce the need for universal service
funding to serve some hard-to-reach areas, and lower the cost of serving some rural households
by as much as several dollars per month which could mean real savings on consumers' bills.
We expect these benefits to occur, and would be concerned and would seriously consider
modifying our approach to this issue if we did not see evidence that these benefits were indeed
occurring.
Today's Order is a testament to the strengths of our federal system and the importance of
states as laboratories for policy development. Thanks to the thoughtful work of a number of
states in crafting pole attachment rules over the last two decades, we have several effective
models for pole attachment governance with proven track records. Our rules incorporate best
practices from Oregon, Utah, New York, and other states.
While the Pole Attachments Order brings one proceeding to a close, we are
simultaneously opening a new proceeding on Accelerating Broadband Deployment. This
proceeding will examine key challenges and best practices for rights-of-way and wireless
22

Federal Communications Commission

FCC 11-51
facilities siting policies. Rights-of-way policies are the rules that govern access to the public
spaces where broadband infrastructure including wireless towers and antennas are deployed,
including roadways, sidewalks, public lands, and public buildings, but excluding utility poles.
This proceeding is focused on improving these policies in order to enable broadband
providers to expand the reach and accelerate deployment of robust, affordable broadband to all
Americans. The National Broadband Plan and our Technological Advisory Council have
identified a number of potential barriers in this area, including:

Poor coordination across jurisdictions on infrastructure issues, which delays broadband
build-out and raises consumer costs;

The expense and complexity of obtaining access to public rights of way;

The fact that it's much harder than it should be to put another antenna on an existing cell
tower;

Failure to embrace "dig-once" policies that save money when workers dig a trench in the
ground to lay fiber or cable; and

Non-standard, confusing permitting processes for broadband infrastructure siting on
federal property.
We will examine these issues with input from all interested parties, including states and
localities, Tribes, other federal agencies, broadband providers, equipment providers, and
consumer advocates. I look forward to learning what's working and can be replicated more
broadly; what's not working and should be fixed; and, in general, what can be done to improve
inefficient or burdensome policies.
I thank the staff, particularly the Wireline and Wireless Bureaus, for their hard work on these
complex and important items. And I thank the TAC, and the FCC staff working with the TAC, for
their continued efforts to develop proposals for further reform
23

Federal Communications Commission

FCC 11-51

STATEMENT OF

COMMISSIONER MICHAEL J. COPPS

Re:
Implementation of Section 224 of the Act, WC Docket No. 07-245, A National Broadband
Plan for Our Future
, GN Docket No. 09-51
Re:
Acceleration of Broadband Deployment: Expanding the Reach and Reducing the Cost of
Broadband Deployment by Improving the Policies Regarding Public Rights of Way and
Wireless Facilities Siting,
WC Docket No. 11- 59
The National Broadband Plan clearly and rightly identified pole attachment policy as a
key part of ensuring that all Americans have access to robust and affordable broadband service.
It's not sexy or very exciting and you can quickly get lost in the weeds, but clarifying the rules
surrounding rates and access to poles has been on the Commission's to-do list for longer than I've
been here--and that's a long time. Pole attachments are without a doubt one of the critical inputs
when communications providers assess the economics of deploying advanced
telecommunications networks. Now, finally, and thanks to the leadership of the Chairman and
the hard work of the staff, we can check it off the list. Today's action should do a lot to promote
our ambitious broadband deployment goals. And, by the way, accelerating the roll out of
advanced telecommunications services is exciting.
Our experience over the past fifteen years has demonstrated a need for a more detailed
framework to govern pole attachments. I believe these revisions of the pole attachment rules will
promote a more competitive broadband market and spur broadband's availability throughout the
country. To that end, we establish a more balanced process to ensure timely and non-
discriminatory access to poles for both wireline and wireless attachers, which will go a long way
toward removing uncertainty and minimizing delays that have frustrated deployment. The
disparities in pole attachment rates for different providers have also been a source of confusion
and litigation, and hopefully the clarity we add today will discourage such outcomes. The
provision in this item of a mechanism to ensure that incumbent local exchange carriers will have
a forum to seek Commission remedies for rates that they believe to be unjust and unreasonable is
a good step in the right direction.
We should always be mindful of, and build upon, the successful experiences at local and
state levels. This much we know: in order to spread the wonders of broadband to every corner of
this country we are going to need a set of best practices in place that will both expand the reach
and reduce the costs of deployment. While we spirit ahead to make broadband a reality, we need
to be cognizant of the authority that local, state and Tribal entities have over rights-of-way and
the siting of wireless facilities. In beginning this conversation today with the Notice of Inquiry
just presented by the Bureau, we need to be mindful of not impinging on local rights as we keep
our important broadband objectives front-and-center. We need the right questions asked, the
right data gathered and the input from all the relevant stakeholders. Getting high-speed, value-
laden broadband out to every citizen in the land is, if it is to become reality, a partnership
exercise--just as all the major infrastructure build-outs in this country have been, going back to
the very beginning. That means the private sector and the public sector--the pubic sector
including the federal, state and local levels. Working together, we can get this job done and keep
the United States a world leader in technology, innovation and consumer opportunity.
My thanks to the Bureau for its hard work here and to the Chairman for bringing us
another critical component of the National Broadband Plan.
24

Federal Communications Commission

FCC 11-51

STATEMENT OF

COMMISSIONER ROBERT M. McDOWELL

Re:
Implementation of Section 224 of the Act, WC Docket No. 07-245, A National Broadband
Plan for Our Future
, GN Docket No. 09-51
Re:
Acceleration of Broadband Deployment: Expanding the Reach and Reducing the Cost of
Broadband Deployment by Improving the Policies Regarding Public Rights of Way and
Wireless Facilities Siting,
WC Docket No. 11- 59
While not the most exciting of issues, the Commission's pole attachment rules are
nonetheless critical to our nation's broadband deployment effort. I, therefore, commend the
Chairman for re-opening the pole attachment debate last spring and following through with some
concrete decisions.
Our action today will help promote continued broadband deployment throughout our
country.1 Our guidance regarding so-called "make ready work" will provide more certainty, help
streamline the process and ultimately speed new entrants' efforts to deploy broadband. Also, the
Commission's use of its authority under Section 224 of the Act to adopt a new
telecommunications pole rental rate formula - generally lowering the attachment rate to the
current "cable rate" - will more effectively encourage competition in broadband deployment.
In concept, I would have liked to have seen a similar move to parity in regard to pole
attachment rental rates for ILECS. But I understand that not all of the ILECS may be similarly
situated vis--vis their competitors, because the ILECs are also pole owners and may enjoy
certain benefits due to their joint use agreements with the utilities. On the other hand, this order
still does provide some relief to ILECs and their customers, where appropriate. Pursuant to our
action today, the ILECs will now have an opportunity to file complaints with the FCC and argue
why the rates, terms or conditions in their agreements with the utilities are not just and
reasonable, as allowed by Section 224.
Regarding a related matter before us today, I hope the Notice of Inquiry on public rights
of way solicits useful information that can assist the FCC's continued efforts to encourage
broadband deployment. I caution, however, that the FCC should be mindful of its limitations and
only use this information in areas where it has jurisdiction.
In sum, I commend all of the staff who worked so diligently on all of these infrastructure
issues and look forward to working with my colleagues as we learn from the various stakeholders
who file in response to the notice.


1 The nationwide effect of this order is limited. For example, the Commission can only exert jurisdiction
over pole attachment issues in areas where these access issues are not regulated by a state. See 47 U.S.C.
224(c). Also, pole attachment arrangements that involve cooperatives are not under our jurisdiction. See
47 U.S.C. 224(a)(1). Nevertheless, each incremental move will make a difference in America's broadband
deployment numbers.
25

Federal Communications Commission

FCC 11-51

STATEMENT OF

COMMISSIONER MIGNON L. CLYBURN

Re:
Implementation of Section 224 of the Act, WC Docket No. 07-245, A National Broadband
Plan for Our Future
, GN Docket No. 09-51
Re:
Acceleration of Broadband Deployment: Expanding the Reach and Reducing the Cost of
Broadband Deployment by Improving the Policies Regarding Public Rights of Way and
Wireless Facilities Siting,
WC Docket No. 11- 59
Today we take an important step to promote broadband deployment and competition, and
both wireline and wireless consumers stand to gain. Through our adoption of specific timeframes
for access to poles, broadband providers will be better positioned to plan their network
deployments and upgrades. As a result, they will be better able to serve their customers and meet
their broadband demands. Moreover, by addressing the disparate pole rental rates paid by service
providers, we are establishing a more evenhanded opportunity for providers to compete with one
another based on their offerings and prices.
I spent a great deal of time considering the arguments on both sides concerning the joint
use agreements that utilities and incumbent local exchange carriers ("ILECs") rely upon for
access to one another's poles. At face value, parity for ILECs is an attractive proposition,
especially considering the policy rationale of a level playing field for all broadband competitors.
However, I was persuaded that joint use agreements are not just simple pole attachment contracts.
They are joint ownership agreements. Some of these agreements have significant histories, as
they are decades old. Accordingly, I agree with the guidelines we establish in this Order that set
forth a series of factors for the Commission to consider in determining whether the existing rates
are just and reasonable in a complaint proceeding. To the extent that ILECs benefit from our
oversight of these agreements through decreased pole expenses, consumers should be the
beneficiaries through additional deployment, decreases in service prices, or network upgrades to
faster broadband speeds. As such, it is only appropriate that industry provide us with regular
updates on how they are passing these benefits on to consumers.
I also support the Notice of Inquiry we adopt today that seeks detailed information on the
management of public rights of ways and the siting of wireless facilities. I believe it is important
for the Commission to gather this data as part of our Broadband Acceleration Initiative.
While it is essential to learn how long it takes and how much it costs for broadband providers to
obtain the necessary approvals from a local jurisdiction to build a new tower or access conduit
under a street, I believe it is equally imperative for the Commission to fully understand the policy
rationales for these processes and costs. Gathering and analyzing the data should not be done in a
vacuum. We must also commit ourselves, to work in partnership, with our counterparts in state
and local governments, other federal agencies, and Tribal governments on these issues. We can
achieve our common goal of promoting broadband service to residents and anchor institutions by
working together.
26

Federal Communications Commission

FCC 11-51

STATEMENT OF

COMMISSIONER MEREDITH ATTWELL BAKER

Re:
Implementation of Section 224 of the Act, WC Docket No. 07-245, A National Broadband
Plan for Our Future
, GN Docket No. 09-51
Re:
Acceleration of Broadband Deployment: Expanding the Reach and Reducing the Cost of
Broadband Deployment by Improving the Policies Regarding Public Rights of Way and
Wireless Facilities Siting,
WC Docket No. 11- 59
There are very few concrete steps this Commission can take to promote broadband
deployment. The pole attachment proceeding is one of them, and I support our efforts to provide
greater certainty and competitive parity in the pole attachment process. We must always act in a
manner that reflects the critical safety and reliability interests of the utilities, and I believe we
struck the proper balance in this Order.
We take important steps to provide clarity to all stakeholders on wireless attachment
rates, timelines, and pole top access issues. The ability to leverage utility poles may be critical
for next-generation wireless build-out to fill coverage holes, to more efficiently re-use spectrum,
and to take advantage of distributed antenna systems. This is the type of action needed to help us
achieve our collective goal of nationwide 4G coverage, and promote greater mobile broadband
competition and efficient spectrum policy. We importantly make clear that utilities retain their
statutory right to ensure the safety and reliability of their core networks. I expect wireless
operators and utilities to work collaboratively to protect electric networks while facilitating access
to these new technologies and services.
I also support the effort to raise the profile of important rights of way issues in the
accompanying Notice of Inquiry. While our authority to act in this area is limited, the
Commission does have a role to highlight impediments to broadband deployment, and I am
hopeful we can partner with industry, states and localities to address these challenges together.
27

Note: We are currently transitioning our documents into web compatible formats for easier reading. We have done our best to supply this content to you in a presentable form, but there may be some formatting issues while we improve the technology. The original version of the document is available as a PDF, Word Document, or as plain text.

close
FCC

You are leaving the FCC website

You are about to leave the FCC website and visit a third-party, non-governmental website that the FCC does not maintain or control. The FCC does not endorse any product or service, and is not responsible for, nor can it guarantee the validity or timeliness of the content on the page you are about to visit. Additionally, the privacy policies of this third-party page may differ from those of the FCC.