Saver Media, Inc., Notice Of Apparent Liability

Download Options

Released: July 31, 2014

Federal Communications Commission

DA 14-1099

Before the

Federal Communications Commission

Washington, D.C. 20554

In re Application of



Saver Media, Inc.


Facility ID No. 190414


NAL/Account No. MB-201441410029

to Modify the Construction Permit for


FRN: 0022637102

KQTC(FM), Eldorado, Texas


File No. BMPH-20130725ADU




Adopted: July 31, 2014


July 31, 2014

By the Chief, Audio Division, Media Bureau:




We have before us an application (“Application”) filed by Saver Media, Inc. (“Saver”) to

modify the construction permit for KQTC(FM), Eldorado, Texas (“Station”). We also have before us an

Informal Objection (“Objection”) filed by Danny Ray Boyer (“Boyer”).1 For the reasons set forth below,

we find that Saver apparently willfully and repeatedly violated Section 319(a) of the Communications Act

of 1934, as amended (“Act”),2 by prematurely constructing facilities proposed in the Application. We

conclude that Saver is apparently liable for a monetary forfeiture in the amount of ten thousand dollars

($10,000).3 We also grant in part and deny in part the Objection, and grant the Application.




Tony Cuellar (“Cuellar”) was the winning bidder for the Eldorado, Texas allotment in

FM Auction 93.4 Cuellar timely filed an application (“2012 CP Application”) for a construction permit

for a new FM station at Eldorado, Texas.5 Boyer filed a Petition to Deny this application. Therein, he

claimed that Cuellar had attempted to or intended to deceive the Commission regarding a past felony

conviction. We denied the Petition to Deny and granted the 2012 CP Application on February 20, 2013.6

1 Boyer filed a Supplement to Informal Objection (“Supplement”) on January 23, 2014. Tony Cuellar (“Cuellar”) –

one of the principals of Saver – filed responses on February 3, 2014 and May 9, 2014.

2 47 U.S.C. § 319(a).

3 We issue this Notice of Apparent Liability pursuant to Sections 319(a) and 503(b) of the Communications Act of

1934, as amended ("Act"), and Section 1.80 of the Commission's rules ("Rules"). See 47 U.S.C. §§ 319(a), 503(b);

47 C.F.R. § 1.80. We have delegated authority to do so under Section 0.283 of the Rules. See 47 C.F.R. § 0.283.

4 Auction of FM Broadcast Construction Permits Closes, Winning Bidders Announced for Auction 93, Public Notice,

27 FCC Rcd 4056 (WTB/MB 2012).

5 File No. BNPH-20120529ALB.

6 Letter from Peter H. Doyle, Chief, Audio Division, Media Bureau, to Anthony T. Lepore, Esq. and Lee J.

Peltzman, Esq. (dated Feb. 20, 2013).


Federal Communications Commission

DA 14-1099

Shortly thereafter, Cuellar filed an application (“Assignment Application”) to assign the Station’s

construction permit to Saver. The Assignment Application indicated that Saver was a Texas corporation

owned by Cuellar and his wife.7 Boyer did not oppose this application. We granted it on April 10, 2013.

A few months later, Saver filed the Application. Boyer then filed the Objection. Therein, he asserts that

Saver engaged in premature construction of the facilities proposed in the Application and that Saver

violated certain Federal Aviation Administration (“FAA”) rules regarding tower lighting. He also alleges

that Saver and/or Cuellar misrepresented facts to the Commission in the 2012 CP Application and the

Assignment Application.




Premature Construction


Section 319(a) of the Act states, in pertinent part, that “[n]o license shall be issued under

the Authority of this Act for the operation of any station unless a permit for its construction has been

granted by the Commission.”8 Section 319 was enacted to ensure that applicants do not use incurred

expenses as a means of exerting improper pressure upon the Commission to grant an application.9 It

forecloses the Commission from issuing a license when the “entire station” has been constructed prior to

the grant of a construction permit.10 This prohibition on premature construction of a broadcast station is

not absolute though. The Commission has sanctioned certain types of pre-authorization construction,

including site clearance, pouring of concrete footings for a tower, installation of a tower base and anchors,

installation of a new power line, purchase and on-site storage (but not installation) of radio equipment and

other preliminary steps having no intrinsic broadcast use.11 Pre-authorization construction of towers or

installation of radio antennas, however, is strictly prohibited.12


Boyer alleges that Saver prematurely constructed the facility proposed in the Application

in violation of Section 319(a) of the Act.13 He submits evidence that Saver has constructed the tower on

which it proposes to mount the Station’s transmitter and has taken delivery of a transmitter building.

Boyer notes that this tower is approved for the frequency assigned to the Station and no others. Thus, he

argues that “the tower has no other purpose other than to serve this proposed facility.”14 Saver does not

dispute that it constructed the tower. Instead, it explains that it plans to lease space on the tower to other

7 File No. BAPH-20130228AKP.

8 47 U.S.C. § 319(a).

9 See, e.g., Patton Communications Corp., Letter, 81 FCC 2d 336, 337 (1980) (“Patton”); WSAV, Inc.,

Memorandum Opinion and Order, 19 FCC 736 (1955), aff’d sub nom. WJIV-TV, Inc. v. FCC, 231 F.2d 725 (D.C.

Cir 1956).

10 Christian Broadcasting of the Midlands, Inc., Order, 103 FCC 2d 375, 378 ¶ 5 (1986) (“Christian Broadcasting”).

11 See, e.g. Manahawkin Communications Corp., Memorandum Opinion and Order, 17 FCC Rcd 342, 355-56 ¶ 22

(2001) (premature construction does not warrant denial of the application) ; Wendell & Associates, Memorandum

Opinion and Order, 14 FCC Rcd 1671, 1679-80 ¶ 24 (1998). See also MCI Communications Corporation, Order

and Notice of Apparent Liability, 3 FCC Rcd 509, 509 ¶ 5 (1988), modified, Supplemental Order, 4 FCC Rcd 7299

(1988), appeal dismissed by judgment sub nom., TeleSTAR, Inc. v. FCC, 901 F.2d 1131 (D.C. Cir. 1990); Christian

Broadcasting, 103 FCC 2d at 377 ¶ 3, Patton, 81 FCC 2d at 337-38.

12 Westinghouse Broadcasting Co., Inc., Memorandum Opinion and Order, 49 FCC 2d 1171, 1173 ¶¶ 12-13 (1974),

Merrimack Valley Communications, Inc., Memorandum Opinion and Order, 20 FCC 2d 161, 163 ¶¶ 8-9 (1969),

rehearing denied, Memorandum Opinion and Order, 21 FCC 2d 440 (1970).

13 Objection at 2-3.

14 Objection at 3.



Federal Communications Commission

DA 14-1099

entities for the provision of other communications services.15 Saver acknowledges that the tower is not

yet approved for the frequencies utilized by these other services but states that it will have all frequencies

approved by the Federal Aviation Administration (“FAA”) prior to installation of any equipment on the

tower. Finally, Saver notes that it has not mounted the Station’s antenna on the tower.


Saver appears to be arguing that it constructed the tower for a legitimate alternative

purpose and thus did not violate the prohibition against premature construction. However, Saver has not

adequately demonstrated that it constructed the tower for any such purpose. For instance, Saver mentions

leasing tower space to another company for installation of a “wireless internet hub” but does not offer a

copy of any agreement with that company. In addition, Saver does not identify any other Commission

licensees authorized to use the tower. Given this, we find that Saver apparently willfully and repeatedly

violated Section 319 of the Act.


Tower Lighting


Section 303(q) of the Act states that antenna structure owners shall maintain the lighting

of antenna structures as prescribed by the Commission.16 Based on FAA recommendations, the

Commission requires that antenna structures exceeding 200 feet above ground level be lit with red

obstruction lighting at night.17 It also has specified that, during construction of an antenna structure for

which red obstruction lighting is required, at least two red obstruction lights must be installed at the

uppermost point of the structure.18 In addition, as the height of the antenna structure exceeds each level at

which permanent obstruction lights will be required, the Commission requires that two similar lights be

installed at each such level. If an obstruction light on an antenna structure is extinguished or

malfunctioning and such extinguishment or malfunction is not corrected within 30 minutes, the

Commission requires the owner of the antenna structure to immediately report this to the nearest Flight

Service Station or office of the FAA.19


Boyer alleges that, at various times during its construction, the tower lacked temporary or

permanent obstruction lighting and that this violated Commission rules governing tower lighting.20 In

response, Saver states that the medium intensity strobe system required by the FAA was installed and

fully operation as of January 25, 2014.21 Saver submits an email from its technical consultant explaining

that he was unable to install the system at the time the tower reached 200 feet about ground level because

the manufacturer “had not yet shipped” it.22 The consultant notes that, as specified in Section 17.48 of the

Rules, he contacted the Flight Service Station and requested issuance of a Notice to Airmen (“NOTAM”).

He indicates that he contacted the Flight Service Station and obtained two additional NOTAMs, the last

of which was valid through January 25, 2014.


We find that Saver complied with the Commission’s rules governing tower lighting.

While the tower did not have obstruction lighting or did not have all required obstruction lighting at

15 Letter from Tony Cuellar to Rodolfo F. Bonacci, Assistant Chief, Audio Division, Media Bureau (rec’d Feb. 3,


16 47 U.S.C. § 303(q).

17 47 C.F.R. §17.21.

18 47 C.F.R. § 17.45.

19 47 C.F.R. § 17.48.

20 Supplement at 3.

21 February Letter at 1.

22 See Electronic Message from John Parle to Rodolfo F. Bonacci, Assistant Chief, Audio Division, Media Bureau

(rec’d Jan. 22, 2014).



Federal Communications Commission

DA 14-1099

various times during its construction, Saver – via its consultant – took the steps required to ensure that the

lack of lighting was reported to the FAA and that NOTAMs were issued.




Boyer alleges that Saver and/or Cuellar made misrepresentations to the Commission in

two earlier applications related to the Station, which we granted on February 20, and April 10, 2013.23

Boyer essentially seeks to indirectly challenge our grants of these applications. The deadlines for filing

petitions for reconsideration of these grants expired well before Boyer filed the Objection on September

20, 2013. Because the time period for filing petitions for reconsideration is prescribed by statute, 24 the

Commission may not, with one extremely narrow exception not applicable here, waive or extend the

filing period.25 We find – as the Commission has – that indirect challenges to Commission decisions

adopted in proceedings in which the right to review has expired are considered impermissible collateral

attacks and are properly denied.26


Proposed Forfeiture

10. Under Section 503(b)(1)(B) of the Act, a person who is found to have willfully or repeatedly

failed to comply with any provision of the Act or any rule, regulation, or order issued by the Commission

shall be liable to the United States for a forfeiture penalty.27 Section 312(f)(1) of the Act defines willful

as “the conscious and deliberate commission or omission of [any] act, irrespective of any intent to

violate” the law.28 The legislative history to Section 312(f)(1) of the Act clarifies that this definition of

willful applies to both Sections 312 and 503(b) of the Act,29 and the Commission has so interpreted the

term in the Section 503(b) context.30 Section 312(f)(2) of the Act provides that “[t]he term ‘repeated,’

23 Specifically, Boyer claims that, despite his representations to the contrary, Cuellar lacked reasonable assurance of

the availability of the site specified in his application for the Station’s existing construction permit. Boyer also

claims that Cuellar and Saver falsely certified that Saver Media Inc. existed at the time they filed an application to

assign the Station’s license to Saver. We granted the former application on February 20, 2013 and the latter

application on April 10, 2013. See Letter from Peter H. Doyle, Chief, Audio Division, Media Bureau, to Anthony T.

Lepore, Esq. and Lee J. Peltzman, Esq. (dated Feb. 20, 2013); Broadcast Actions, Public Notice, Report No. 47968

(rel. April 16, 2013).

24 47 U.S.C. § 405(a) (“A petition for reconsideration must be filed within thirty days from the date upon which

public notice is given of the order, decision, report or action complained of.”).

25 See Reuters Ltd. v. FCC, 781 F.2d 946, 952 (D.C. Cir. 1986) (“[W]e conclude that the Commission acted beyond

its lawful authority when it entertained the belated petition for reconsideration.”). See also Metromedia Inc.,

Memorandum Opinion and Order, 56 FCC 2d 909, 909-10 ¶ 2 (1975) (Commission may not waive 30-day filing

period to accept a petition for reconsideration filed one day late); Fortuna Systems Corp., Order on Reconsideration,

3 FCC Rcd 5122, 5123 ¶ 9(CCB 1988). Specifically, the courts have held that the Commission may not accept

untimely reconsideration petitions in the absence of extremely unusual circumstances. See, e.g., Virgin Islands Tel.

Corp. v. FCC, 989 F.2d 1231, 1237 (D.C. Cir. 1993).

26 See, e.g., MCI Telecommunications Corp. v. Pacific Northwest Bell Telephone Co., Memorandum Opinion and

Order, 5 FCC Rcd 216, 228 n.38 (1990), recon. denied, 5 FCC Rcd 3463 (1990), appeal dismissed sub nom.

Mountain States Tel. and Tel. Co. v. FCC, 951 F.2d 1259 (10th Cir. 1991) (per curiam).

27 47 U.S.C. § 503(b)(1)(B). See also 47 C.F.R. 1.80(a)(1).

28 47 U.S.C. § 312(f)(1).

29 See H.R. Rep. No. 97-765, 97th Cong. 2d Sess. 51 (1982).

30 See Southern California Broadcasting Co., Memorandum Opinion and Order, 6 FCC Rcd 4387, 4388 (1991)

recon denied, 7 FCC Rcd 3454 (1992).



Federal Communications Commission

DA 14-1099

when used with reference to the commission or omission of any act, means the commission or omission

of such act more than once or, if such commission or omission is continuous, for more than one day.”31

11. The Commission’s Forfeiture Policy Statement and Section 1.80(b)(8) of the Rules establish

a base forfeiture amount of $10,000 for construction and operation without an instrument of

authorization.32 In determining the appropriate forfeiture amount, we may adjust the base amount upward

or downward by considering the factors enumerated in Section 503(b)(2)(D) of the Act, including “the

nature, circumstances, extent and gravity of the violation, and, with respect to the violator, the degree of

culpability, any history of prior offenses, ability to pay, and such other matters as justice may require.”33.

Considering the record as a whole and all of the factors required by Section 503(b)(2)(D) of the Act and

the Forfeiture Policy Statement, we believe that a $10,000 forfeiture is appropriate here.34 Specifically,

Saver did prematurely construct the facilities proposed in the Application. In addition, Saver did not

disclose the premature construction to the Commission voluntarily. 35




It appearing that no further substantial question concerning the Application remains, and

that the public interest will be served by authorization of the facilities applied for, we will grant the

Application. Accordingly, IT IS ORDERED that the application to modify the construction permit of

KQTC(FM), Eldorado, Texas, filed by Saver Media, Inc. (File No. BMPH-20130725ADU) IS


13. IT IS FURTHER ORDERED, pursuant to Section 503(b) of the Communications Act of

1934, as amended, and Section 1.80 of the Commission’s Rules, that Saver Media, Inc., is hereby

NOTIFIED of its APPARENT LIABILITY FOR FORFEITURE in the amount of ten thousand dollars

($10,000) for its apparent willful and repeated violation of Section 319(a) of the Communications Act of

1934, as amended.

14. IT IS FURTHER ORDERED, pursuant to Section 1.80 of the Commission’s Rules, that,

within thirty (30) days of the release date of this NAL, Saver Media, Inc. SHALL PAY the full amount of

the proposed forfeiture or SHALL FILE a written statement seeking reduction or cancellation of the

proposed forfeiture.

15. Payment of the proposed forfeiture must be made by check or similar instrument, payable to

the order of the Federal Communications Commission. The payment must include the NAL/Acct. No.

31 47 U.S.C. § 312(f)(2).

32 See Forfeiture Policy Statement and Amendment of Section 1.80(b) of the Rules to Incorporate the Forfeiture

Guidelines, Report and Order, 12 FCC Rcd 17087, 17113-15 (1997) (“Forfeiture Policy Statement”), recon. denied,

15 FCC Rcd 303 (1999); 47 C.F.R. § 1.80(b)(8), note to paragraph (b)(8), Section I.

33 47 U.S.C. § 503(b)(2)(D); see also Forfeiture Policy Statement, 12 FCC Rcd at 17100; 47 C.F.R. § 1.80(b)(8).

34 See, e.g., Davidson Media, Memorandum Opinion and Order and Notice of Apparent Liability for Forfeiture, 21

FCC Rcd 8492 (MB 2006) (proposing a $4,000 forfeiture for six missing issues and programs lists).

35 See Rasa Communications Corp., Letter, 11 FCC Rcd 13243 (MMB 1996) (proposing a $7500 forfeiture for

unauthorized construction and operation where the facilities actually constructed varied little from those authorized

by the Commission and presented only a “slight” threat to air navigation and a “slight” threat of radio interference,

and the permittee voluntarily disclosed the unauthorized construction and operation to the Commission) (“Rasa”);

Spectrum Broadcasting Corp., Letter, 12 FCC Rcd 7724 (MMB 1997) (proposing $10,000 forfeiture for

unauthorized construction and operation where there was voluntary disclosure of the unauthorized construction and

operation but a greater variance between the facilities actually constructed and those authorized than in Rasa and

where, unlike Rasa, the antenna was mounted at a higher elevation than authorized); California State University at

Sacramento, Letter, 14 FCC Rcd 3825 (MMB 1999) (proposing a $5000 forfeiture despite variation between

constructed facilities and authorized facilities that was more substantial than in Rasa because the violation was

limited to unauthorized construction and was voluntarily disclosed).



Federal Communications Commission

DA 14-1099

and FRN No. referenced in the caption above. Payment by check or money order may be mailed to

Federal Communications Commission, at P.O. Box 979088, St. Louis, MO


Payment by

overnight mail may be sent to U.S. Bank—Government Lockbox #979088, SL-MO-C2-GL, 1005

Convention Plaza, St. Louis, MO 63101. Payment by wire transfer may be made to ABA Number

021030004, receiving bank: TREAS NYC, BNF: FCC/ACV--27000001 and account number as expressed

on the remittance instrument.

If completing the FCC Form 159, enter the NAL/Account number in block

number 23A (call sign/other ID), and enter the letters “FORF” in block number 24A (payment type code).

Licensee will also send electronic notification on the date said payment is made to

16. The response, if any, must be mailed to Office of the Secretary, Federal Communications

Commission, 445 12th Street, S.W., Washington DC 20554, ATTN: Peter H. Doyle, Chief, Audio

Division, Media Bureau, and MUST INCLUDE the NAL/Acct. No. referenced above.

17. The Commission will not consider reducing or canceling a forfeiture in response to a claim of

inability to pay unless the respondent submits: (1) federal tax returns for the most recent three-year

period; (2) financial statements prepared according to generally accepted accounting practices (“GAAP”);

or (3) some other reliable and objective documentation that accurately reflects the respondent’s current

financial status. Any claim of inability to pay must specifically identify the basis for the claim by

reference to the financial documentation submitted.


Requests for full payment of the forfeiture proposed in this NAL under the installment

plan should be sent to: Associate Managing Director-Financial Operations, 445 12th Street, S.W., Room

1-A625, Washington, DC 20554.36


IT IS FURTHER ORDERED that copies of this NAL shall be sent, by First Class and

Certified Mail, Return Receipt Requested, to Saver Media, Inc., 601 Culwell Street, San Angelo, Texas

76903, and to its counsel, John C. Trent, Esq., Putbrese Hunsaker & Trent, P.C., 200 South Church Street,

Woodstock, Virginia 22664.


IT IS FURTHER ORDERED that the Informal Objection filed by Danny Ray Boyer on

September 20, 2013 IS GRANTED IN PART and otherwise DENIED.


Peter H. Doyle

Chief, Audio Division

Media Bureau

36 See 47 C.F.R. § 1.1914.


Note: We are currently transitioning our documents into web compatible formats for easier reading. We have done our best to supply this content to you in a presentable form, but there may be some formatting issues while we improve the technology. The original version of the document is available as a PDF, Word Document, or as plain text.


You are leaving the FCC website

You are about to leave the FCC website and visit a third-party, non-governmental website that the FCC does not maintain or control. The FCC does not endorse any product or service, and is not responsible for, nor can it guarantee the validity or timeliness of the content on the page you are about to visit. Additionally, the privacy policies of this third-party page may differ from those of the FCC.